This study aims to design a mine drainage system to overcome the problem of inundation on the pit floor due to high rainfall. Based on hydrological analysis using 15 years of rainfall data (2009-2023), the Gumbel distribution method was selected with a planned rainfall of 75 mm, rainfall intensity of 16.38 mm/hour, and rainfall return period of 2 years. There are four rainfall catchments in the pit area, and the mine drainage system design includes open channels, culverts and settling ponds. The dimensions of the channels and culverts are designed based on the runoff water discharge of each DTH. The settling pond consists of three compartments with a maintenance time of 100-1292 days. This design is expected to be effective in managing runoff water to support mine operations. Keywords: Goodness of Fit, Mine Conveyance System, Settling Ponds

Authors

Institutions

Publication Details

Journal
KURVATEK
Published
2025-04-29
DOI
https://doi.org/10.33579/krvtk.v10i1.5529
Primary Topic
Water and Land Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

RANCANGAN SISTEM PENYALIRAN TAMBANG PADA TAMBANG BIJIH NIKEL PIT HILL ANYER

Zulfikar Aulia Alisaputra Alisaputra, Peter Eka Rosadi
KURVATEK
Water and Land Management
article

RANCANGAN SISTEM PENYALIRAN TAMBANG PADA TAMBANG BIJIH NIKEL PIT HILL ANYER

Zulfikar Aulia Alisaputra Alisaputra, Peter Eka Rosadi
article en

Abstract

This study aims to design a mine drainage system to overcome the problem of inundation on the pit floor due to high rainfall. Based on hydrological analysis using 15 years of rainfall data (2009-2023), the Gumbel distribution method was selected with a planned rainfall of 75 mm, rainfall intensity of 16.38 mm/hour, and rainfall return period of 2 years. There are four rainfall catchments in the pit area, and the mine drainage system design includes open channels, culverts and settling ponds. The dimensions of the channels and culverts are designed based on the runoff water discharge of each DTH. The settling pond consists of three compartments with a maintenance time of 100-1292 days. This design is expected to be effective in managing runoff water to support mine operations. Keywords: Goodness of Fit, Mine Conveyance System, Settling Ponds

KURVATEKVol. 10(1)
Universitas Teknologi Yogyakarta (ID), Universitas Pembangunan Nasional Veteran Yogyakarta (ID)
Openalex Percentile: Top 87%
Water and Land Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.