De-Risking a Heavy Oil Project Development Through an Early Production System

Abstract This paper discusses in detail the Atlanta Early Production System (EPS) strategy to de-risk the Atlanta field development. The Atlanta is a post-salt oil field, located in the Santos Basin, BS-4 Block, approximately 185 km from coast of Rio de Janeiro, Brazil, in water depths of 1,550 meters, represents one of the most challenging heavy oil developments in ultra-deep waters. The EPS phase, initiated in May 2018 with FPSO Petrojarl 1 adapted by Altera (former Teekay) designed as a crucial step to validate key technical aspects, collect reservoir data, and reduce uncertainties before the Full Field Development (FFD) phase, while generating some revenue to the company. Introduction"Discovered in 2001, the Atlanta Field represents a unique technical challenge in ultra-deepwater development. The field comprises an unconsolidated sandstone reservoir at a temperature of 105.8°F (41°C) at −2,315 m, with 800 m of overburden thickness in a 1,550m water depth environment. The Eocene interval exhibits exceptional petrophysical properties, characterized by high net-to-gross sands (82-94%) with an average porosity of 36% and permeability ranging from 4 to 6 Darcy. These excellent rock properties, however, are offset by the challenging fluid characteristics: heavy oil (14° API), high viscosity (228 cP at reservoir conditions), and highly acidic content (total acid number of 9.8 mg KOH/g). These characteristics demanded innovative solutions for artificial lift, flow assurance, and topside processing facilities." (Marsili, 2015) To ensure its economic feasibility, the development concept required a good well productivity, sand control, completion, high power artificial lift pumping system, specific flow assurance procedures, and most importantly, an experienced operational team.

Authors

Publication Details

Journal
Offshore Technology Conference
Published
2025-04-28
DOI
https://doi.org/10.4043/35679-ms
Primary Topic
Reservoir Engineering and Simulation Methods
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

De-Risking a Heavy Oil Project Development Through an Early Production System

Franciele Caroline de Assis Valadão, Josiane Gagno, Ivan Rongel
Offshore Technology Conference
Reservoir Engineering and Simulation Methods
article

De-Risking a Heavy Oil Project Development Through an Early Production System

Franciele Caroline de Assis Valadão, Josiane Gagno, Ivan Rongel
article en

Abstract

Abstract This paper discusses in detail the Atlanta Early Production System (EPS) strategy to de-risk the Atlanta field development. The Atlanta is a post-salt oil field, located in the Santos Basin, BS-4 Block, approximately 185 km from coast of Rio de Janeiro, Brazil, in water depths of 1,550 meters, represents one of the most challenging heavy oil developments in ultra-deep waters. The EPS phase, initiated in May 2018 with FPSO Petrojarl 1 adapted by Altera (former Teekay) designed as a crucial step to validate key technical aspects, collect reservoir data, and reduce uncertainties before the Full Field Development (FFD) phase, while generating some revenue to the company. Introduction"Discovered in 2001, the Atlanta Field represents a unique technical challenge in ultra-deepwater development. The field comprises an unconsolidated sandstone reservoir at a temperature of 105.8°F (41°C) at −2,315 m, with 800 m of overburden thickness in a 1,550m water depth environment. The Eocene interval exhibits exceptional petrophysical properties, characterized by high net-to-gross sands (82-94%) with an average porosity of 36% and permeability ranging from 4 to 6 Darcy. These excellent rock properties, however, are offset by the challenging fluid characteristics: heavy oil (14° API), high viscosity (228 cP at reservoir conditions), and highly acidic content (total acid number of 9.8 mg KOH/g). These characteristics demanded innovative solutions for artificial lift, flow assurance, and topside processing facilities." (Marsili, 2015) To ensure its economic feasibility, the development concept required a good well productivity, sand control, completion, high power artificial lift pumping system, specific flow assurance procedures, and most importantly, an experienced operational team.

Offshore Technology Conference
Openalex Percentile: Top 72%
Reservoir Engineering and Simulation Methods
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.