Enabling Shipyard Delivery Through Project and Organizational Strategic Management

Abstract Exmar and ENI's project management approach to delivering the Congo LNG phase one (Tango and Excalibur) assets, enabling on-time liquid gas delivery, is a best-in-class example of how management can enable project success through team structure, collaboration, compromise, and vision and unlock potential in the offshore sector. Phase one of offshore Congo LNG development, operated by Exmar for owner ENI, is the first natural gas liquefaction (LNG) project in the Republic of Congo. The development of new infrastructure (gas compression plant, pipelines, and offshore (Floating Natural Gas Liquefaction (FLNG) terminal allows ENI Congo to develop the Marine XII concession resources (the Nene and Litchendjili fields) to serve the local Congolese electricity markets and exports gas exports to Europe. The project's development scheme is in two phases and involves using multiple technological and operational skills. The first phase is the nearshore development, with the positioning of the Tango FLNG floating unit jointly moored to the Excalibur FSU, collectively the offshore LNG terminal. Phase one faced a challenging shipyard conversion component of the project, completed at Dry Docks World Dubai between April and October 2023. The on-time delivery of the two-vessel conversion allows the first liquid gas parcel, allocated to Piombino's regasification terminal in Italy, to be delivered in Congo by the end of 2023. The on-time asset sail-away is a significant industry accomplishment that has contributed to the project's overall success. The schedule for conversion of both the Tango FLNG and Excalibur assets was aggressive and fast-track, driving the site team's structure to adopt a non-conventional, truly integrated management approach, with a delivery mindset instilled in all team members. The nuances of the organization and the management strategies of the site team approach (quick integration of team members, trust, no-blame culture, integrated owner/contractor team, onsite decision-making authority, amongst others) were key enablers to the project's success and supported the overall objectives. The techniques used to ensure site team excellence will be presented and discussed.

Authors

Institutions

Publication Details

Journal
Offshore Technology Conference
Published
2025-04-28
DOI
https://doi.org/10.4043/35935-ms
Primary Topic
Outsourcing and Supply Chain Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Enabling Shipyard Delivery Through Project and Organizational Strategic Management

Thomas P. Mackey, Melissa J. Murphy
Offshore Technology Conference
Outsourcing and Supply Chain Management
article

Enabling Shipyard Delivery Through Project and Organizational Strategic Management

Thomas P. Mackey, Melissa J. Murphy
article en

Abstract

Abstract Exmar and ENI's project management approach to delivering the Congo LNG phase one (Tango and Excalibur) assets, enabling on-time liquid gas delivery, is a best-in-class example of how management can enable project success through team structure, collaboration, compromise, and vision and unlock potential in the offshore sector. Phase one of offshore Congo LNG development, operated by Exmar for owner ENI, is the first natural gas liquefaction (LNG) project in the Republic of Congo. The development of new infrastructure (gas compression plant, pipelines, and offshore (Floating Natural Gas Liquefaction (FLNG) terminal allows ENI Congo to develop the Marine XII concession resources (the Nene and Litchendjili fields) to serve the local Congolese electricity markets and exports gas exports to Europe. The project's development scheme is in two phases and involves using multiple technological and operational skills. The first phase is the nearshore development, with the positioning of the Tango FLNG floating unit jointly moored to the Excalibur FSU, collectively the offshore LNG terminal. Phase one faced a challenging shipyard conversion component of the project, completed at Dry Docks World Dubai between April and October 2023. The on-time delivery of the two-vessel conversion allows the first liquid gas parcel, allocated to Piombino's regasification terminal in Italy, to be delivered in Congo by the end of 2023. The on-time asset sail-away is a significant industry accomplishment that has contributed to the project's overall success. The schedule for conversion of both the Tango FLNG and Excalibur assets was aggressive and fast-track, driving the site team's structure to adopt a non-conventional, truly integrated management approach, with a delivery mindset instilled in all team members. The nuances of the organization and the management strategies of the site team approach (quick integration of team members, trust, no-blame culture, integrated owner/contractor team, onsite decision-making authority, amongst others) were key enablers to the project's success and supported the overall objectives. The techniques used to ensure site team excellence will be presented and discussed.

Offshore Technology Conference
Murphy Oil Corporation (United States) (US), ExxonMobil (United States) (US)
Openalex Percentile: Top 65%
Outsourcing and Supply Chain Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.