APLIKASI VALUE ENGINEERING PADA PEKERJAAN TAMBAH KURANG UNTUK MENINGKATKAN EFISIENSI BIAYA KONTRAKTOR (Studi Kasus: Gedung D BPOM Jakarta)

Cost planning is one of the important things in a development project, both for theproject owner and the implementing contractor. The contractor has a planned costtarget at the tender stage, however, changes in costs may occur during theimplementation period due to additional or less work and resulting in changes incosts. To be able to achieve the cost efficiency target, this can be done by carryingout value engineering. The stages of the value engineering method consist of theinformation stage, function analysis stage, creativity stage, evaluation stage,development stage and recommendation stage. The application of value engineeringin the BPOM Building D Construction Project can provide an increase cost and stillmaintain function. Contractor get cost efficiency of IDR 1,528,657,929,- or 2.52%,while the project owner gets a cost efficiency of IDR 1,182,279,319 or 1.66%.

Authors

Institutions

Publication Details

Journal
Wahana Teknik Sipil Jurnal Pengembangan Teknik Sipil
Published
2024-12-01
DOI
https://doi.org/10.32497/wahanats.v29i2.6155
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

APLIKASI VALUE ENGINEERING PADA PEKERJAAN TAMBAH KURANG UNTUK MENINGKATKAN EFISIENSI BIAYA KONTRAKTOR (Studi Kasus: Gedung D BPOM Jakarta)

Sumirin Sumirin, Kartono Wibowo, Indra Hidayat
Wahana Teknik Sipil Jurnal Pengembangan Teknik Sipil
Management and Optimization Techniques
article

APLIKASI VALUE ENGINEERING PADA PEKERJAAN TAMBAH KURANG UNTUK MENINGKATKAN EFISIENSI BIAYA KONTRAKTOR (Studi Kasus: Gedung D BPOM Jakarta)

Sumirin Sumirin, Kartono Wibowo, Indra Hidayat
article en

Abstract

Cost planning is one of the important things in a development project, both for theproject owner and the implementing contractor. The contractor has a planned costtarget at the tender stage, however, changes in costs may occur during theimplementation period due to additional or less work and resulting in changes incosts. To be able to achieve the cost efficiency target, this can be done by carryingout value engineering. The stages of the value engineering method consist of theinformation stage, function analysis stage, creativity stage, evaluation stage,development stage and recommendation stage. The application of value engineeringin the BPOM Building D Construction Project can provide an increase cost and stillmaintain function. Contractor get cost efficiency of IDR 1,528,657,929,- or 2.52%,while the project owner gets a cost efficiency of IDR 1,182,279,319 or 1.66%.

Wahana Teknik Sipil Jurnal Pengembangan Teknik SipilVol. 29(2)
Sultan Agung Islamic University (ID)
Openalex Percentile: Top 49%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.