Electrical Resistivity Tomography as a Geotechnical Justification Support (Case Study Makassar – Pare-Pare Railway Bed Construction KM 68+450 to KM 68+750)

This study examined the presence of underground water channels under the Makassar - Pare-pare railway line KM 68+450 – KM 68+750 and the design concept for the technical solution. The potential for underground water channels was identified during construction, based on community information, the location's morphological phenomena, and geological conditions whose base rock was the limestone formation. The problems can cause instability of the railway line, resulting in unsafe train travel. One of the characteristics of limestone rock conditions is its hollow shape, like a cave that can become underground water flow. It was a case study whose solution was based on data obtained from geotechnical investigations. Boring testing can only provide information on soil layers at the test point and cannot describe soil stratigraphy section, including underground water channel. Combination ERT and Boring tests were carried out to examine the presence of underground water channels. This study was conducted in three stages: initial identification, advanced identification, and design concept of Technical Solution. In these three stages, data collection and analysis were carried out. The results of the study indicated that ERT tests could provide a picture of the subsurface to shallow bedrock, thus facilitating the justification of geotechnical design. From the analysis, it was concluded that no channel cavities, such as caves, that function as underground water channels. The existing water flow was estimated to be a confining aquifer where water flows due to the height difference in the surrounding morphological conditions through the media of the broken limestone water shaft. It was confirmed with the results of Boring and ERT tests. The proposed technical solution concept was strengthening the Dolken embankment structure and geogrid, combined with a subdrain layer. The technical solution was prepared based on the results of research on construction contract data and project resource readiness.

Authors

Publication Details

Journal
INERSIA lnformasi dan Ekspose Hasil Riset Teknik Sipil dan Arsitektur
Published
2024-12-15
DOI
https://doi.org/10.21831/inersia.v20i2.77380
Primary Topic
Geotechnical and construction materials studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Electrical Resistivity Tomography as a Geotechnical Justification Support (Case Study Makassar – Pare-Pare Railway Bed Construction KM 68+450 to KM 68+750)

Endaryanta Endaryanta, Sabrianto Aswad, Nur Alfian Sasmayaputra, Yuli Fajarwati et al.
1 links
INERSIA lnformasi dan Ekspose Hasil Riset Teknik Sipil dan Arsitektur
Geotechnical and construction materials studies
article

Electrical Resistivity Tomography as a Geotechnical Justification Support (Case Study Makassar – Pare-Pare Railway Bed Construction KM 68+450 to KM 68+750)

Endaryanta Endaryanta, Sabrianto Aswad, Nur Alfian Sasmayaputra, Yuli Fajarwati, Dian Eksana Wibowo, Nur Oktaviani Widiastuti
article en

Abstract

This study examined the presence of underground water channels under the Makassar - Pare-pare railway line KM 68+450 – KM 68+750 and the design concept for the technical solution. The potential for underground water channels was identified during construction, based on community information, the location's morphological phenomena, and geological conditions whose base rock was the limestone formation. The problems can cause instability of the railway line, resulting in unsafe train travel. One of the characteristics of limestone rock conditions is its hollow shape, like a cave that can become underground water flow. It was a case study whose solution was based on data obtained from geotechnical investigations. Boring testing can only provide information on soil layers at the test point and cannot describe soil stratigraphy section, including underground water channel. Combination ERT and Boring tests were carried out to examine the presence of underground water channels. This study was conducted in three stages: initial identification, advanced identification, and design concept of Technical Solution. In these three stages, data collection and analysis were carried out. The results of the study indicated that ERT tests could provide a picture of the subsurface to shallow bedrock, thus facilitating the justification of geotechnical design. From the analysis, it was concluded that no channel cavities, such as caves, that function as underground water channels. The existing water flow was estimated to be a confining aquifer where water flows due to the height difference in the surrounding morphological conditions through the media of the broken limestone water shaft. It was confirmed with the results of Boring and ERT tests. The proposed technical solution concept was strengthening the Dolken embankment structure and geogrid, combined with a subdrain layer. The technical solution was prepared based on the results of research on construction contract data and project resource readiness.

INERSIA lnformasi dan Ekspose Hasil Riset Teknik Sipil dan ArsitekturVol. 20(2)
Openalex Percentile: Top 67%
Geotechnical and construction materials studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.