Schedule Information Modeling for Forensic Analysis and Assessment of Time Claims

The contemporary landscape of construction projects witnesses a notable inclination toward heightened complexity and specialization, contributing to an increase in both the frequency and intricacy of construction claims. Among these, disputes concerning schedule impacts emerge as the most prevalent, yet also the most intricate and least comprehended. Existing methodologies for analysis persist as costly, time-consuming, and complex, often failing to accurately address impacts of delays lasting less than a day. In response to these shortcomings, this study introduces a novel framework termed Forensic Schedule Information Modeling (ForSIM) designed specifically for the analysis of time-related claims within construction projects. ForSIM adopts key principles derived from window-based analytical techniques, thereby incorporating established methodologies within its structure. Additionally, ForSIM adopts a time-step simulation approach, which serves as a foundational mechanism for both the modeling and integration of project data. Through this approach, ForSIM streamlines the process of automated data integration, analysis, and the quantification of both acceleration and time extension awards. Moreover, it provides detailed demonstrations of causation, thereby enhancing clarity in dispute resolution processes. A prototype of ForSIM has undergone rigorous development and testing procedures, elucidating its effectiveness in addressing the constraints associated with prevailing methodologies. The findings of this study highlight the transformative potential of ForSIM in augmenting industry practices, facilitating more efficient and accurate evaluations of time claims within construction projects.

Authors

Institutions

Publication Details

Journal
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Published
2025-04-25
DOI
https://doi.org/10.1061/jladah.ladr-1239
Primary Topic
Business Process Modeling and Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Schedule Information Modeling for Forensic Analysis and Assessment of Time Claims

Simaan AbouRizk, Muaz Fagiar, Yasser Mohamed
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Business Process Modeling and Analysis
article

Schedule Information Modeling for Forensic Analysis and Assessment of Time Claims

Simaan AbouRizk, Muaz Fagiar, Yasser Mohamed
article en

Abstract

The contemporary landscape of construction projects witnesses a notable inclination toward heightened complexity and specialization, contributing to an increase in both the frequency and intricacy of construction claims. Among these, disputes concerning schedule impacts emerge as the most prevalent, yet also the most intricate and least comprehended. Existing methodologies for analysis persist as costly, time-consuming, and complex, often failing to accurately address impacts of delays lasting less than a day. In response to these shortcomings, this study introduces a novel framework termed Forensic Schedule Information Modeling (ForSIM) designed specifically for the analysis of time-related claims within construction projects. ForSIM adopts key principles derived from window-based analytical techniques, thereby incorporating established methodologies within its structure. Additionally, ForSIM adopts a time-step simulation approach, which serves as a foundational mechanism for both the modeling and integration of project data. Through this approach, ForSIM streamlines the process of automated data integration, analysis, and the quantification of both acceleration and time extension awards. Moreover, it provides detailed demonstrations of causation, thereby enhancing clarity in dispute resolution processes. A prototype of ForSIM has undergone rigorous development and testing procedures, elucidating its effectiveness in addressing the constraints associated with prevailing methodologies. The findings of this study highlight the transformative potential of ForSIM in augmenting industry practices, facilitating more efficient and accurate evaluations of time claims within construction projects.

Journal of Legal Affairs and Dispute Resolution in Engineering and ConstructionVol. 17(3)
University of Alberta (CA), HipKnee Arkansas Foundation (US)
Gender equality
Openalex Percentile: Top 86%
Business Process Modeling and Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Schedule Information Modeling for Forensic Analysis and Assessment of Time Claims — Simaan AbouRizk, Muaz Fagiar, et al. · Journal of Legal Affairs and Dispute Resolution in Engineering and Construction (2025) | TGRS Research Map | TGRS