ANALISIS PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM) (Studi Kasus: Peningkatan Jalan Patrol – Palintang Kabupaten Bandung)

Project control is a crucial management activity, especially given the complexity of project-related issues. Effective management is needed to ensure that projects, such as the improvement of the Patrol-Palintang road in Bandung Regency, adhere to the planned schedule. The objective of this research is to assess cost and time performance using the Earned Value Management (EVM) method. The data utilized in this study includes the Budget Plan (RAB), S-Curve, Time Schedule, and Weekly Reports. The analysis results from the Earned Value Management method indicate that the time performance is less than one (SPI < 1), with an average SPI value of 0.929. This means that the time performance is poor, indicating delays in project completion relative to the planned schedule. Conversely, the cost performance index is above one, with an average CPI value of 1.0014. This indicates excellent cost performance, as the actual costs incurred are lower than the earned value, demonstrating no wastage of resources.

Authors

Publication Details

Journal
Jurnal Teknik Sipil
Published
2024-11-30
DOI
https://doi.org/10.36546/tekniksipil.v14i2.1473
Primary Topic
Urban Transport Systems Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM) (Studi Kasus: Peningkatan Jalan Patrol – Palintang Kabupaten Bandung)

Ignatius Sudarsono, Fauzia Mulyawati, Rizha Rafli Ghifari
Jurnal Teknik Sipil
Urban Transport Systems Analysis
article

ANALISIS PENGENDALIAN WAKTU DAN BIAYA DENGAN METODE EARNED VALUE MANAGEMENT (EVM) (Studi Kasus: Peningkatan Jalan Patrol – Palintang Kabupaten Bandung)

Ignatius Sudarsono, Fauzia Mulyawati, Rizha Rafli Ghifari
article en

Abstract

Project control is a crucial management activity, especially given the complexity of project-related issues. Effective management is needed to ensure that projects, such as the improvement of the Patrol-Palintang road in Bandung Regency, adhere to the planned schedule. The objective of this research is to assess cost and time performance using the Earned Value Management (EVM) method. The data utilized in this study includes the Budget Plan (RAB), S-Curve, Time Schedule, and Weekly Reports. The analysis results from the Earned Value Management method indicate that the time performance is less than one (SPI < 1), with an average SPI value of 0.929. This means that the time performance is poor, indicating delays in project completion relative to the planned schedule. Conversely, the cost performance index is above one, with an average CPI value of 1.0014. This indicates excellent cost performance, as the actual costs incurred are lower than the earned value, demonstrating no wastage of resources.

Jurnal Teknik SipilVol. 14(2)
Openalex Percentile: Top 67%
Urban Transport Systems Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.