Factors influencing construction delays in public investment civil projects: The case of Hanoi, Vietnam

Construction delays in public investment civil projects remain a critical challenge in many developing cities, including Hanoi, Vietnam. This study aims to investigate and rank the key factors influencing these delays, providing evidence-based insights for improving project performance. A quantitative research approach was adopted using a structured questionnaire survey targeting 152 construction professionals, including project owners, contractors, consultants, and regulatory authorities. The Relative Importance Index (RII) method was employed to evaluate the significance of seven identified delay factors. The results indicate that contractor capacity (RII = 0.854), supervision consultant capacity (RII = 0.814), and the legal framework for public investment (RII = 0.762) are the most influential contributors to delays. In contrast, socio-economic (RII = 0.720) and natural conditions (RII = 0.700) exert less impact. Based on these findings, the study proposes practical recommendations such as improving contractor evaluation and supervision practices and streamlining legal procedures. The findings have significant implications for policymakers and stakeholders seeking to enhance the effectiveness of public investment in infrastructure, particularly in rapidly urbanizing environments. This research also enriches the global body of knowledge on delay mitigation in public construction projects within emerging economies.

Authors

Institutions

Publication Details

Journal
Edelweiss Applied Science and Technology
Published
2025-04-24
DOI
https://doi.org/10.55214/25768484.v9i4.6547
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Factors influencing construction delays in public investment civil projects: The case of Hanoi, Vietnam

Pham Thi My Dung, Nguyễn Quốc Toản, Tran Thi Lien, Nguyen Thi Thuy et al.
Edelweiss Applied Science and Technology
Construction Project Management and Performance
article

Factors influencing construction delays in public investment civil projects: The case of Hanoi, Vietnam

Pham Thi My Dung, Nguyễn Quốc Toản, Tran Thi Lien, Nguyen Thi Thuy, Nguyen Thi My Hanh, Pham Thuy Linh, Trinh Khanh Huyen, Nguyen Yen Nhi
article en

Abstract

Construction delays in public investment civil projects remain a critical challenge in many developing cities, including Hanoi, Vietnam. This study aims to investigate and rank the key factors influencing these delays, providing evidence-based insights for improving project performance. A quantitative research approach was adopted using a structured questionnaire survey targeting 152 construction professionals, including project owners, contractors, consultants, and regulatory authorities. The Relative Importance Index (RII) method was employed to evaluate the significance of seven identified delay factors. The results indicate that contractor capacity (RII = 0.854), supervision consultant capacity (RII = 0.814), and the legal framework for public investment (RII = 0.762) are the most influential contributors to delays. In contrast, socio-economic (RII = 0.720) and natural conditions (RII = 0.700) exert less impact. Based on these findings, the study proposes practical recommendations such as improving contractor evaluation and supervision practices and streamlining legal procedures. The findings have significant implications for policymakers and stakeholders seeking to enhance the effectiveness of public investment in infrastructure, particularly in rapidly urbanizing environments. This research also enriches the global body of knowledge on delay mitigation in public construction projects within emerging economies.

Edelweiss Applied Science and TechnologyVol. 9(4)
National Economics University (VN), Hanoi University of Business and Technology (VN), Hanoi University (VN)
Center for the Environment, Harvard University
Openalex Percentile: Top 90%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.