An Examination on Project Cost Overruns in Project Management: A Study of S3 Project at Kanshanshi Mine

This study examines project cost overruns in project management with a focus on S3 Project at Kanshanshi Mine. The main objectives were to identify types of cost overruns, assess their effects on project management, and evaluate the effectiveness of cost strategies. A descriptive research design was employed, with a sample of 50 respondents. Findings review that poor project planning, inefficient resource allocation and scope changes are significant causes of cost overruns. Inaccurate cost estimation and inadequate risk management contributes to project delays and budget issues. The study recommends thorough project planning, efficient resource allocation, and effective risk management practices to mitigate cost overruns. Additionally, fostering stakeholder collaboration and using metrics like Earned Value Management (EVM), Cost Performance Index (CPI), and Schedule Performance Index (SPI) can enhance project cost strategy success.

Authors

Publication Details

Journal
Journal of arts, humanities and social science.
Published
2025-04-24
DOI
https://doi.org/10.69739/jahss.v2i1.417
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An Examination on Project Cost Overruns in Project Management: A Study of S3 Project at Kanshanshi Mine

Kelvin Chibomba, Kapangu Chola
Journal of arts, humanities and social science.
Mining Techniques and Economics
article

An Examination on Project Cost Overruns in Project Management: A Study of S3 Project at Kanshanshi Mine

Kelvin Chibomba, Kapangu Chola
article en

Abstract

This study examines project cost overruns in project management with a focus on S3 Project at Kanshanshi Mine. The main objectives were to identify types of cost overruns, assess their effects on project management, and evaluate the effectiveness of cost strategies. A descriptive research design was employed, with a sample of 50 respondents. Findings review that poor project planning, inefficient resource allocation and scope changes are significant causes of cost overruns. Inaccurate cost estimation and inadequate risk management contributes to project delays and budget issues. The study recommends thorough project planning, efficient resource allocation, and effective risk management practices to mitigate cost overruns. Additionally, fostering stakeholder collaboration and using metrics like Earned Value Management (EVM), Cost Performance Index (CPI), and Schedule Performance Index (SPI) can enhance project cost strategy success.

Journal of arts, humanities and social science.Vol. 2(1)
Openalex Percentile: Top 91%
Mining Techniques and Economics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.