ANALYSIS OF NETWORK ON THE DEVELOPMENT OF PT. JINGGA PROPERTI HOUSES IN SIGI BIROMARU

Project management is used to plan, implement, and control project activities to minimize risks to project time and cost. Completion of an infrastructure project on time is a top priority. One of the problems that often occurs is the time delay of the project caused by the incompatibility of the schedule planning with the character of human resources, building materials, disasters, company regulations that can result in construction failure and have an impact on costs. Type of the research was descriptive quantitative, quantitative, and qualitative data sources. Planning for the construction of subsidized type 36 houses using Gant cart takes 75.5 days/604.5 hours in the construction of 1 unit of subsidized housing. This study aims to determine and analyze the network of construction of subsidized type 36 houses at PT. Jingga Properti Indonesia in Kalukubula Sigi Biromaru using the PERT (Project Evaluation Review Technique) method both in manual calculations and the assistance of POM-QM Software, the results of the research obtained that the construction of subsidized type 36 houses at PT. Jingga Property Indonesia can be completed in 400.47 hours. The results of the realization of house construction before the calculation using the PERT method were 538 hours. If targeted for 420 hours, the possibility of completion is 99%. The proposed schedule of 294.52 hours can be realized if the masons are added/more activities are done simultaneously.

Authors

Institutions

Publication Details

Journal
TADULAKO INTERNATIONAL JOURNAL OF APPLIED MANAGEMENT
Published
2024-12-20
DOI
https://doi.org/10.59769/tajam.v6i3.141
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALYSIS OF NETWORK ON THE DEVELOPMENT OF PT. JINGGA PROPERTI HOUSES IN SIGI BIROMARU

Saharuddin Kaseng, Syamsuddin Syamsuddin, Endang Suerni
1 links
TADULAKO INTERNATIONAL JOURNAL OF APPLIED MANAGEMENT
BIM and Construction Integration
article

ANALYSIS OF NETWORK ON THE DEVELOPMENT OF PT. JINGGA PROPERTI HOUSES IN SIGI BIROMARU

Saharuddin Kaseng, Syamsuddin Syamsuddin, Endang Suerni
article en

Abstract

Project management is used to plan, implement, and control project activities to minimize risks to project time and cost. Completion of an infrastructure project on time is a top priority. One of the problems that often occurs is the time delay of the project caused by the incompatibility of the schedule planning with the character of human resources, building materials, disasters, company regulations that can result in construction failure and have an impact on costs. Type of the research was descriptive quantitative, quantitative, and qualitative data sources. Planning for the construction of subsidized type 36 houses using Gant cart takes 75.5 days/604.5 hours in the construction of 1 unit of subsidized housing. This study aims to determine and analyze the network of construction of subsidized type 36 houses at PT. Jingga Properti Indonesia in Kalukubula Sigi Biromaru using the PERT (Project Evaluation Review Technique) method both in manual calculations and the assistance of POM-QM Software, the results of the research obtained that the construction of subsidized type 36 houses at PT. Jingga Property Indonesia can be completed in 400.47 hours. The results of the realization of house construction before the calculation using the PERT method were 538 hours. If targeted for 420 hours, the possibility of completion is 99%. The proposed schedule of 294.52 hours can be realized if the masons are added/more activities are done simultaneously.

TADULAKO INTERNATIONAL JOURNAL OF APPLIED MANAGEMENTVol. 6(3)
Tadulako University (ID)
Openalex Percentile: Top 69%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALYSIS OF NETWORK ON THE DEVELOPMENT OF PT. JINGGA PROPERTI HOUSES IN SIGI BIROMARU — Saharuddin Kaseng, Syamsuddin Syamsuddin, et al. · TADULAKO INTERNATIONAL JOURNAL OF APPLIED MANAGEMENT (2024) | TGRS Research Map | TGRS