No-wait lines optimisation: a procedure based on scheduling enhanced by digital twin

Abstract The no-wait scheduling problem involves planning the sequence of tasks in a job without any delay. This constraint is crucial in industries where production interruptions may create significant inefficiencies or quality issues. This paper addresses this problem by proposing a new methodology to design and verify a work-cycle related layout, focusing on both job-shop and flow-shop environments and finally proving its efficiency thanks to the use of a digital twin to validate the production process. The goal of the optimisation is the makespan minimisation and it is achieved through the application of the timetabling heuristic method. The iterative nature of the proposed model allows for a continuous improvement in scheduling, and queue reduction is verified thanks to the digital twin. The iterative procedure is tested on a real galvanic no-wait line of a primary aerospace international company; results show that the methodology application guarantees respect to the no-wait constraint and the minimisation of the production times, which concur to increase the demand satisfaction for the company.

Authors

Institutions

Publication Details

Journal
Flexible Services and Manufacturing Journal
Published
2025-04-22
DOI
https://doi.org/10.1007/s10696-025-09611-y
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

No-wait lines optimisation: a procedure based on scheduling enhanced by digital twin

Stefano de Miranda, Marcello Fera, Mario Caterino, Roberto Macchiaroli
Flexible Services and Manufacturing Journal
Scheduling and Optimization Algorithms
article

No-wait lines optimisation: a procedure based on scheduling enhanced by digital twin

Stefano de Miranda, Marcello Fera, Mario Caterino, Roberto Macchiaroli
article en

Abstract

Abstract The no-wait scheduling problem involves planning the sequence of tasks in a job without any delay. This constraint is crucial in industries where production interruptions may create significant inefficiencies or quality issues. This paper addresses this problem by proposing a new methodology to design and verify a work-cycle related layout, focusing on both job-shop and flow-shop environments and finally proving its efficiency thanks to the use of a digital twin to validate the production process. The goal of the optimisation is the makespan minimisation and it is achieved through the application of the timetabling heuristic method. The iterative nature of the proposed model allows for a continuous improvement in scheduling, and queue reduction is verified thanks to the digital twin. The iterative procedure is tested on a real galvanic no-wait line of a primary aerospace international company; results show that the methodology application guarantees respect to the no-wait constraint and the minimisation of the production times, which concur to increase the demand satisfaction for the company.

Flexible Services and Manufacturing Journal
University of Salerno (IT), University of Campania "Luigi Vanvitelli" (IT)
Università degli Studi della Campania Luigi Vanvitelli
Openalex Percentile: Top 89%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.