Application of Value Engineering in Lecture Buildings (Case Study Joint Lecture Building, Campus C, Airlangga University, Surabaya)

ver time, construction projects in Indonesia as a developing country have become increasingly complex and require large costs and require more attention to proper time and resource management. The Joint Lecture Building, Campus C, Airlangga University, Surabaya, with a project cost of IDR 8,300,000.00/m2 is considered to exceed the standard cost of similar buildings in Surabaya, which is IDR 6,250,000.00/m², so it requires a cost efficiency evaluation. This study uses a value engineering method by analyzing work items to find alternative materials that are more cost-effective without reducing function and quality. This study was conducted with five stages of value engineering: information, creativity, analysis, development, and recommendations. The results show significant cost savings on several work items such as beam work, floor slabs and columns, achieving a potential reduction of up to 71% of the total existing budget.

Authors

Publication Details

Journal
Journal of Civil Engineering Planning and Design
Published
2024-11-30
DOI
https://doi.org/10.31284/j.jcepd.2024.v3i2.7101
Primary Topic
Value Engineering and Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Application of Value Engineering in Lecture Buildings (Case Study Joint Lecture Building, Campus C, Airlangga University, Surabaya)

Nabila Hadi Sayyidah
Journal of Civil Engineering Planning and Design
Value Engineering and Management
article

Application of Value Engineering in Lecture Buildings (Case Study Joint Lecture Building, Campus C, Airlangga University, Surabaya)

Nabila Hadi Sayyidah
article en

Abstract

ver time, construction projects in Indonesia as a developing country have become increasingly complex and require large costs and require more attention to proper time and resource management. The Joint Lecture Building, Campus C, Airlangga University, Surabaya, with a project cost of IDR 8,300,000.00/m2 is considered to exceed the standard cost of similar buildings in Surabaya, which is IDR 6,250,000.00/m², so it requires a cost efficiency evaluation. This study uses a value engineering method by analyzing work items to find alternative materials that are more cost-effective without reducing function and quality. This study was conducted with five stages of value engineering: information, creativity, analysis, development, and recommendations. The results show significant cost savings on several work items such as beam work, floor slabs and columns, achieving a potential reduction of up to 71% of the total existing budget.

Journal of Civil Engineering Planning and DesignVol. 3(2)
Openalex Percentile: Top 50%
Value Engineering and Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.