PROJECT PLANNING DIVERSION TUNNEL BAGONG DAM PROJECT TRENGGALEK REGENCY

On the progress of construction development, especially in the construction of water buildings, one of which is a dam. In Trenggalek Regency a dam was built which was named Bagong Dam. This dam was built to control floods that commonly occur in the area. In the dam construction project there is a diversion tunnel building that is used to divert water flow during the main dam construction period. There were delays in the construction of this evasive building. The tunnel is a limited space, the difficulty of access roads, and equipment damage in some activities cause delays in the project so that it requires proper and efficient project planning. To complete this project, good cost, time, and quality considerations are needed so that it can be realized properly. This project planning aims to plan the organizational structure, strategies and methods, site layout preparation assisted using autocad application and Microsoft excel, quality plan, K3 plan, implementation budget plan, and scheduling using Microsoft Project 2021 application. Pure organizational structure planning is more efficient. By using a comparison of the use of existing and precast, it is found that the use of precast has a faster implementation duration of 180 days while if using the existing for 259 days. In the calculation of the implementation budget plan in precast amounting to Rp170,021,748,985 and in the existing obtained at Rp188,495,961,368. With these results, it is found that the use of precast is cheaper and more effective in the process. Quality planning is carried out according to the quality targets that have been made so that the building is according to plan. OHS planning is carried out to achieve Zero Accident. Effective site layout preparation is carried out for work efficiency.

Authors

Publication Details

Journal
Jurnal JOS-MRK
Published
2025-03-17
DOI
https://doi.org/10.33795/jos-mrk.v6i1.6027
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

PROJECT PLANNING DIVERSION TUNNEL BAGONG DAM PROJECT TRENGGALEK REGENCY

Indah Ria Riskiyah, Fadjar Purnomo, Vidi Az Zahra
Jurnal JOS-MRK
Mining Techniques and Economics
article

PROJECT PLANNING DIVERSION TUNNEL BAGONG DAM PROJECT TRENGGALEK REGENCY

Indah Ria Riskiyah, Fadjar Purnomo, Vidi Az Zahra
article en

Abstract

On the progress of construction development, especially in the construction of water buildings, one of which is a dam. In Trenggalek Regency a dam was built which was named Bagong Dam. This dam was built to control floods that commonly occur in the area. In the dam construction project there is a diversion tunnel building that is used to divert water flow during the main dam construction period. There were delays in the construction of this evasive building. The tunnel is a limited space, the difficulty of access roads, and equipment damage in some activities cause delays in the project so that it requires proper and efficient project planning. To complete this project, good cost, time, and quality considerations are needed so that it can be realized properly. This project planning aims to plan the organizational structure, strategies and methods, site layout preparation assisted using autocad application and Microsoft excel, quality plan, K3 plan, implementation budget plan, and scheduling using Microsoft Project 2021 application. Pure organizational structure planning is more efficient. By using a comparison of the use of existing and precast, it is found that the use of precast has a faster implementation duration of 180 days while if using the existing for 259 days. In the calculation of the implementation budget plan in precast amounting to Rp170,021,748,985 and in the existing obtained at Rp188,495,961,368. With these results, it is found that the use of precast is cheaper and more effective in the process. Quality planning is carried out according to the quality targets that have been made so that the building is according to plan. OHS planning is carried out to achieve Zero Accident. Effective site layout preparation is carried out for work efficiency.

Jurnal JOS-MRKVol. 6(1)
Openalex Percentile: Top 92%
Mining Techniques and Economics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.