Innovative BWM–TOPSIS-based approach to determine the optimum delivery method for offshore projects

Offshore projects hold significant importance in the construction industry by fostering innovation, enabling large-scale infrastructure development, and supporting the expansion of renewable energy sources, enhancing global energy security and economic stability. Effective risk management is crucial in offshore projects to ensure operational safety, sustainability, and financial viability by identifying, assessing, and mitigating potential hazards. Selecting an appropriate project delivery method (PDM) is pivotal for efficient risk management, as it facilitates the proper allocation and mitigation of risks throughout the construction process. This study aims to investigate the impact of PDM on the risk assessment of the lifecycle of offshore platform projects and to identify and evaluate risks associated with offshore projects to improve understanding and optimize performance outcomes. In order To achieve the study's objective, the Best Worst Method (BWM) and the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) are utilized for a lifecycle-focused risk assessment to identify the optimum PDM for offshore projects. A BWM-TOPSIS system is developed specifically for offshore projects, starting with organizing risks identified from the literature into a Risk Breakdown Structure (RBS) and subsequent evaluation using the Delphi technique for comprehensive and reliable risk analysis. The findings indicate that Integrated Project Delivery (IPD) and Construction Manager at Risk (CMAR) are the most effective methods due to their higher levels of integration, collaboration, and proactive risk management.

Authors

Institutions

Publication Details

Journal
Scientific Reports
Published
2025-04-17
DOI
https://doi.org/10.1038/s41598-025-95710-7
Citations
5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
10.53

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Innovative BWM–TOPSIS-based approach to determine the optimum delivery method for offshore projects

Ehab Tolba, Ahmed M. Ebid, Ibrahim Mahdi, Lamisse Raed et al.
5 citations
Scientific Reports
Construction Project Management and Performance
10.53
article

Innovative BWM–TOPSIS-based approach to determine the optimum delivery method for offshore projects

Ehab Tolba, Ahmed M. Ebid, Ibrahim Mahdi, Lamisse Raed, Hassan Ibrahim
article en
5 citations

Abstract

Offshore projects hold significant importance in the construction industry by fostering innovation, enabling large-scale infrastructure development, and supporting the expansion of renewable energy sources, enhancing global energy security and economic stability. Effective risk management is crucial in offshore projects to ensure operational safety, sustainability, and financial viability by identifying, assessing, and mitigating potential hazards. Selecting an appropriate project delivery method (PDM) is pivotal for efficient risk management, as it facilitates the proper allocation and mitigation of risks throughout the construction process. This study aims to investigate the impact of PDM on the risk assessment of the lifecycle of offshore platform projects and to identify and evaluate risks associated with offshore projects to improve understanding and optimize performance outcomes. In order To achieve the study's objective, the Best Worst Method (BWM) and the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) are utilized for a lifecycle-focused risk assessment to identify the optimum PDM for offshore projects. A BWM-TOPSIS system is developed specifically for offshore projects, starting with organizing risks identified from the literature into a Risk Breakdown Structure (RBS) and subsequent evaluation using the Delphi technique for comprehensive and reliable risk analysis. The findings indicate that Integrated Project Delivery (IPD) and Construction Manager at Risk (CMAR) are the most effective methods due to their higher levels of integration, collaboration, and proactive risk management.

Scientific ReportsVol. 15(1)
Future University in Egypt (EG), Port Said University (EG)
Science and Technology Development Fund
Industry, innovation and infrastructure
Openalex Percentile: Top 2%
Construction Project Management and Performance
10.53
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.