AC Interference and Mitigation at Pipeline Facilities – Case Study

Abstract An AC interference study was conducted in 2021 following a utility development with the addition of a high voltage AC powerline in Alberta, Canada. The study comprised of 11 pipelines and 4 powerlines collocating in several stretches totalling approximately 50 km of collocation, with various crossing locations. In the unmitigated state, the modelling results indicated that mitigation under fault conditions is required at 17 pipeline facilities. This paper discusses the strategies used to optimize the mitigation, considering the facilities specific conditions, some of the challenges faced by the install crews, and the changes to design during construction. The optimized design approach resulted in overall less mitigation requirements, smaller number of site visits, reduced construction footprint and environmental impact, and reduction in the overall project cost.

Authors

Publication Details

Published
2025-04-06
DOI
https://doi.org/10.5006/c2025-00117
Primary Topic
Electrical Fault Detection and Protection
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

AC Interference and Mitigation at Pipeline Facilities – Case Study

Ernesto Gudino, Hycem Bahgat, S.M. Segall
Electrical Fault Detection and Protection
article

AC Interference and Mitigation at Pipeline Facilities – Case Study

Ernesto Gudino, Hycem Bahgat, S.M. Segall
article en

Abstract

Abstract An AC interference study was conducted in 2021 following a utility development with the addition of a high voltage AC powerline in Alberta, Canada. The study comprised of 11 pipelines and 4 powerlines collocating in several stretches totalling approximately 50 km of collocation, with various crossing locations. In the unmitigated state, the modelling results indicated that mitigation under fault conditions is required at 17 pipeline facilities. This paper discusses the strategies used to optimize the mitigation, considering the facilities specific conditions, some of the challenges faced by the install crews, and the changes to design during construction. The optimized design approach resulted in overall less mitigation requirements, smaller number of site visits, reduced construction footprint and environmental impact, and reduction in the overall project cost.

Openalex Percentile: Top 94%
Electrical Fault Detection and Protection
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.