Diagnosis and Analysis of Partial Discharge Fault of 500kv Transformer

In this paper, a typical partial discharge failure of the 500kV transformer in the handover test stage is introduced. According to the local discharge signal characteristics under different pressure modes after fully eliminating external interference, it is preliminarily determined that local discharge has nothing to do with the insulation of the winding end of high and low voltage sides. Combined with the diagnostic test results after returning to the factory and the characteristics of no abnormal oil samples taken for many times, it is speculated that the fault point is not located in the winding, and there may be air gap discharge in the insulating parts. The results of disassembly inspection verify the inferences of local placement, confirm that local closed cavity of corrugated board between high and high voltage side windings leads to low energy discharge, and finally put forward suggestions to prevent similar defects of main transformer.

Authors

Institutions

Publication Details

Published
2025-01-10
DOI
https://doi.org/10.1109/iceaai64185.2025.10957534
Citations
3
Primary Topic
Power Line Inspection Robots
Type
article
Field-Weighted Citation Impact
0.71
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Diagnosis and Analysis of Partial Discharge Fault of 500kv Transformer

Jinghui Ruan, Yun Liu, Ping Peng, Lipeng Zhong et al.
3 citations
Power Line Inspection Robots
0.71
article

Diagnosis and Analysis of Partial Discharge Fault of 500kv Transformer

Jinghui Ruan, Yun Liu, Ping Peng, Lipeng Zhong, Yongheng Zhong
article en
3 citations

Abstract

In this paper, a typical partial discharge failure of the 500kV transformer in the handover test stage is introduced. According to the local discharge signal characteristics under different pressure modes after fully eliminating external interference, it is preliminarily determined that local discharge has nothing to do with the insulation of the winding end of high and low voltage sides. Combined with the diagnostic test results after returning to the factory and the characteristics of no abnormal oil samples taken for many times, it is speculated that the fault point is not located in the winding, and there may be air gap discharge in the insulating parts. The results of disassembly inspection verify the inferences of local placement, confirm that local closed cavity of corrugated board between high and high voltage side windings leads to low energy discharge, and finally put forward suggestions to prevent similar defects of main transformer.

Hunan University (CN)
Openalex Percentile: Top 34%
Power Line Inspection Robots
0.71
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Diagnosis and Analysis of Partial Discharge Fault of 500kv Transformer — Jinghui Ruan, Yun Liu, et al. · (2025) | TGRS Research Map | TGRS