Deconstruction of a prefabricated concrete building designed for disassembly–cost comparison of deconstruction and demolition

Abstract Design for disassembly (DfD) is a suggested concept for enhancing circular economy in the construction sector. To expand the usage of the DfD concept, and especially promote the markets for DfD components, more detailed cost analysis is required of each life-cycle phase. This study estimates the deconstruction and demolition costs of a two-floor day care building, built with prefabricated concrete components. Three alternative scenarios are compared: (1) deconstruction of a building designed for disassembly; (2) deconstruction of a built-as-usual (BAU) building; and (3) demolition of a BAU building. The calculation data is based on data gathered by interviews; the results of a pilot project; and software providing wide cost data of real projects. The results indicate that the deconstruction profitability primarily depends on the number of floors, as both the intermediate floors and interior walls are suitable for reuse, whereas the foundation is typically crushed and disposed. Hence, roughly, the lower the building is, the less profitable the deconstruction is. Despite the advantageous solutions facilitating the deconstruction of DfD buildings, demolition is still a more appealing strategy with its lower cost and shorter duration. This study offers novel information of the deconstruction cost of DfD building, as these expenses have not been previously carefully studied. Here we compare the costs of deconstruction of a DfD building and a BAU building, as well as the demolition option. These results can be utilized for evolving inducement for DfD implementation.

Authors

Institutions

Publication Details

Journal
Environmental Research Infrastructure and Sustainability
Published
2025-04-15
DOI
https://doi.org/10.1088/2634-4505/adcd27
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Deconstruction of a prefabricated concrete building designed for disassembly–cost comparison of deconstruction and demolition

Tuomo Joensuu, Ulrika Uotila, Arto Saari, Pyry Harsunen
Environmental Research Infrastructure and Sustainability
BIM and Construction Integration
article

Deconstruction of a prefabricated concrete building designed for disassembly–cost comparison of deconstruction and demolition

Tuomo Joensuu, Ulrika Uotila, Arto Saari, Pyry Harsunen
article en

Abstract

Abstract Design for disassembly (DfD) is a suggested concept for enhancing circular economy in the construction sector. To expand the usage of the DfD concept, and especially promote the markets for DfD components, more detailed cost analysis is required of each life-cycle phase. This study estimates the deconstruction and demolition costs of a two-floor day care building, built with prefabricated concrete components. Three alternative scenarios are compared: (1) deconstruction of a building designed for disassembly; (2) deconstruction of a built-as-usual (BAU) building; and (3) demolition of a BAU building. The calculation data is based on data gathered by interviews; the results of a pilot project; and software providing wide cost data of real projects. The results indicate that the deconstruction profitability primarily depends on the number of floors, as both the intermediate floors and interior walls are suitable for reuse, whereas the foundation is typically crushed and disposed. Hence, roughly, the lower the building is, the less profitable the deconstruction is. Despite the advantageous solutions facilitating the deconstruction of DfD buildings, demolition is still a more appealing strategy with its lower cost and shorter duration. This study offers novel information of the deconstruction cost of DfD building, as these expenses have not been previously carefully studied. Here we compare the costs of deconstruction of a DfD building and a BAU building, as well as the demolition option. These results can be utilized for evolving inducement for DfD implementation.

Environmental Research Infrastructure and SustainabilityVol. 5(2)
Tampere University of Applied Sciences (FI), Tampere University (FI), Tampere University (FI)
Openalex Percentile: Top 93%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Deconstruction of a prefabricated concrete building designed for disassembly–cost comparison of deconstruction and demolition — Tuomo Joensuu, Ulrika Uotila, et al. · Environmental Research Infrastructure and Sustainability (2025) | TGRS Research Map | TGRS