Analysis of Factors Causing Variation Orders and their Impact on Construction Contract Value of Main Dam Projects

The Indonesian government has been actively engaged in extensive dam construction initiatives aimed at harnessing water resources for diverse purposes such as agricultural irrigation, clean water supply, flood control, power generation, and tourism. However, the construction of each main dam project faces challenges, particularly in the form of variation orders that lead to increases in construction costs. This research investigated the factors contributing to variation orders in main dam projects in Indonesia and to assess their impact on the overall construction costs. A comprehensive literature review was performed to identify variation order factors previously studied by researchers. Subsequently, secondary data were gathered through questionnaires administered to various stakeholders involved in main dam projects, including contractors, consultants, and owners. The analysis of questionnaire responses revealed a total of 26 indicators contributing to variation orders, which were categorized into 9 consultant-related factor, 8 owner-related factor, 6 external factor, and 3 contractor-related factor. Four indicators, including the alignment of tender drawings and field conditions, natural changes (weather/geology), changes in work items, and the complexity of dam design, were identified as having mean values greater than 4 on a 5-point Likert scale. This indicates strong consensus among respondents that these indicators significantly contribute to variation orders. A subsequent questionnaire aimed to evaluate the impact of these 26 variation order indicators on construction cost increases. The collected data from respondents was analyzed using multiple linear regression. The results revealed that the contractor-related factor had the most substantial impact on cost increases with a coefficient of 0.14, followed by the external factor at 0.067, and the owner-related factor at 0.04.

Authors

Publication Details

Journal
ASTONJADRO
Published
2024-09-22
DOI
https://doi.org/10.32832/astonjadro.v13i3.15981
Primary Topic
Evaluation and Optimization Models
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Factors Causing Variation Orders and their Impact on Construction Contract Value of Main Dam Projects

I Putu Artama Wiguna, Hasiholan Christian Siahaan
ASTONJADRO
Evaluation and Optimization Models
article

Analysis of Factors Causing Variation Orders and their Impact on Construction Contract Value of Main Dam Projects

I Putu Artama Wiguna, Hasiholan Christian Siahaan
article en

Abstract

The Indonesian government has been actively engaged in extensive dam construction initiatives aimed at harnessing water resources for diverse purposes such as agricultural irrigation, clean water supply, flood control, power generation, and tourism. However, the construction of each main dam project faces challenges, particularly in the form of variation orders that lead to increases in construction costs. This research investigated the factors contributing to variation orders in main dam projects in Indonesia and to assess their impact on the overall construction costs. A comprehensive literature review was performed to identify variation order factors previously studied by researchers. Subsequently, secondary data were gathered through questionnaires administered to various stakeholders involved in main dam projects, including contractors, consultants, and owners. The analysis of questionnaire responses revealed a total of 26 indicators contributing to variation orders, which were categorized into 9 consultant-related factor, 8 owner-related factor, 6 external factor, and 3 contractor-related factor. Four indicators, including the alignment of tender drawings and field conditions, natural changes (weather/geology), changes in work items, and the complexity of dam design, were identified as having mean values greater than 4 on a 5-point Likert scale. This indicates strong consensus among respondents that these indicators significantly contribute to variation orders. A subsequent questionnaire aimed to evaluate the impact of these 26 variation order indicators on construction cost increases. The collected data from respondents was analyzed using multiple linear regression. The results revealed that the contractor-related factor had the most substantial impact on cost increases with a coefficient of 0.14, followed by the external factor at 0.067, and the owner-related factor at 0.04.

ASTONJADROVol. 13(3)
Openalex Percentile: Top 65%
Evaluation and Optimization Models
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis of Factors Causing Variation Orders and their Impact on Construction Contract Value of Main Dam Projects — I Putu Artama Wiguna, Hasiholan Christian Siahaan · ASTONJADRO (2024) | TGRS Research Map | TGRS