An activity-based lessons learned model to support scheduling decisions in construction

Purpose The aim of this study is to develop an activity-based lessons-learned model that allows construction companies to capture, store, classify and reuse activity-related lessons learned (LL) from previous projects, thereby increasing the reliability of time estimates in scheduling. Design/methodology/approach Scheduling is a knowledge-intensive process that requires the utilization of data and expert opinion elicitation from various levels of an organization in construction projects. This research consists of five successive steps: performing a needs analysis, proposing an activity-based lessons-learned process model, validating the proposed process model, developing a tool to apply the proposed model in a computer environment and testing the applicability of the tool. To implement the proposed model in practice, a web-based tool, namely the Construction Industry Scheduling with Activity-Based Lessons Learned Tool (ConSALL Tool), was developed. Its functionality was evaluated using black-box testing. The tool was then applied in a real construction project. Findings Results show that ConSALL has the potential to improve scheduling decisions in construction projects by incorporating data and experience from previous projects. Findings from this research can be used to develop similar models and AI tools to foster activity-based learning in other project-based industries as well as the construction industry. Originality/value This paper presents an innovative approach to enhancing construction project scheduling by leveraging LL from past projects. The development and application of the ConSALL Tool demonstrate a practical implementation of the proposed model, providing a framework that can be adapted to other industries to improve project planning and execution.

Authors

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2025-04-14
DOI
https://doi.org/10.1108/ecam-06-2024-0729
Citations
1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
1.01
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An activity-based lessons learned model to support scheduling decisions in construction

İrem Dikmen, M. Talat Birgönül, Anıl Yılmaz, Emre Caner Akçay
1 citations
Engineering Construction & Architectural Management
BIM and Construction Integration
1.01
article

An activity-based lessons learned model to support scheduling decisions in construction

İrem Dikmen, M. Talat Birgönül, Anıl Yılmaz, Emre Caner Akçay
article en
1 citations

Abstract

Purpose The aim of this study is to develop an activity-based lessons-learned model that allows construction companies to capture, store, classify and reuse activity-related lessons learned (LL) from previous projects, thereby increasing the reliability of time estimates in scheduling. Design/methodology/approach Scheduling is a knowledge-intensive process that requires the utilization of data and expert opinion elicitation from various levels of an organization in construction projects. This research consists of five successive steps: performing a needs analysis, proposing an activity-based lessons-learned process model, validating the proposed process model, developing a tool to apply the proposed model in a computer environment and testing the applicability of the tool. To implement the proposed model in practice, a web-based tool, namely the Construction Industry Scheduling with Activity-Based Lessons Learned Tool (ConSALL Tool), was developed. Its functionality was evaluated using black-box testing. The tool was then applied in a real construction project. Findings Results show that ConSALL has the potential to improve scheduling decisions in construction projects by incorporating data and experience from previous projects. Findings from this research can be used to develop similar models and AI tools to foster activity-based learning in other project-based industries as well as the construction industry. Originality/value This paper presents an innovative approach to enhancing construction project scheduling by leveraging LL from past projects. The development and application of the ConSALL Tool demonstrate a practical implementation of the proposed model, providing a framework that can be adapted to other industries to improve project planning and execution.

Engineering Construction & Architectural Management
Openalex Percentile: Top 26%
BIM and Construction Integration
1.01
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.