Research on Dynamic Optimization of a Critical Path Based on Stochastic Duration and the Earned Value Method

Critical paths are widely used in project schedule management, but most existing studies ignore the volatility and dynamic characteristics of project duration, which increases the risk of project implementation. This paper proposes a dynamic optimization model of random duration and the EVM (earned value method) based on critical path technology. The random duration based on a lognormal distribution is introduced into critical path technology, and the completion probability model is established to evaluate the fluctuation of the project completion schedule. Then, the earned value correction model is established and combined with performance indicators to improve the dynamic management system of proactive scheme scheduling and reactive scheme scheduling. The proposed method can fully consider the fluctuation and dynamics of the project duration, effectively reduce the errors caused by the uncertain fluctuation of the duration, and further improve scientific management and reduce management costs.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-04-14
DOI
https://doi.org/10.3390/buildings15081285
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on Dynamic Optimization of a Critical Path Based on Stochastic Duration and the Earned Value Method

Zhi Cao, Jiawei Wang, Danyang Li, Ping Cao et al.
Buildings
Resource-Constrained Project Scheduling
article

Research on Dynamic Optimization of a Critical Path Based on Stochastic Duration and the Earned Value Method

Zhi Cao, Jiawei Wang, Danyang Li, Ping Cao, Dinglei Huang
article en

Abstract

Critical paths are widely used in project schedule management, but most existing studies ignore the volatility and dynamic characteristics of project duration, which increases the risk of project implementation. This paper proposes a dynamic optimization model of random duration and the EVM (earned value method) based on critical path technology. The random duration based on a lognormal distribution is introduced into critical path technology, and the completion probability model is established to evaluate the fluctuation of the project completion schedule. Then, the earned value correction model is established and combined with performance indicators to improve the dynamic management system of proactive scheme scheduling and reactive scheme scheduling. The proposed method can fully consider the fluctuation and dynamics of the project duration, effectively reduce the errors caused by the uncertain fluctuation of the duration, and further improve scientific management and reduce management costs.

BuildingsVol. 15(8)
Xi'an University of Science and Technology (CN)
Openalex Percentile: Top 92%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.