Evaluation of Liquefaction Potential in the Budong-Budong Dam Foundation Plan to Prevent Dam Failure Due to Liquefaction Using a Deterministic Approach

The Budong-Budong Dam, located in the district of Central Mamuju, West Sulawesi Province, is currently under construction. The foundation plan of the dam is a layer of river deposits (alluvial) with a thickness of 25 m and a shallow water table depth, which has been shown to have liquefaction potential. This study aims to assess the liquefaction potential of the river deposit layer using some additional SPT test data. This research is expected to confirm the liquefaction potential of the river deposits layer so that it can be considered by the dam owner in determining the foundation excavation limit and prevent dam failure due to liquefaction. The liquefaction potential analysis was carried out using a semi-empirical procedure according to Idriss and Boulanger (2006). The analysis was performed under 2 (two) earthquake conditions, namely Operating Basis Earthquake (OBE) and Safety Evaluation Earthquake (SEE), using different values of fines content (5%, 15%, 35%) and earthquake magnitudes (6.8, 7.0, 7.3, 7.5 and 7.7). The analysis shows that the foundation plan of the Budong-Budong Dam has the potential for liquefaction under both OBE and SEE conditions, which generally occurs at a depth of about 10-12 m from the ground surface. The liquefaction potential of finer-grained river deposits tends to be lower

Authors

Institutions

Publication Details

Journal
Teknik
Published
2025-04-14
DOI
https://doi.org/10.14710/teknik.v46i2.67803
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluation of Liquefaction Potential in the Budong-Budong Dam Foundation Plan to Prevent Dam Failure Due to Liquefaction Using a Deterministic Approach

Sukamta Sukamta, Dicky Erista
Teknik
Geotechnical Engineering and Underground Structures
article

Evaluation of Liquefaction Potential in the Budong-Budong Dam Foundation Plan to Prevent Dam Failure Due to Liquefaction Using a Deterministic Approach

Sukamta Sukamta, Dicky Erista
article en

Abstract

The Budong-Budong Dam, located in the district of Central Mamuju, West Sulawesi Province, is currently under construction. The foundation plan of the dam is a layer of river deposits (alluvial) with a thickness of 25 m and a shallow water table depth, which has been shown to have liquefaction potential. This study aims to assess the liquefaction potential of the river deposit layer using some additional SPT test data. This research is expected to confirm the liquefaction potential of the river deposits layer so that it can be considered by the dam owner in determining the foundation excavation limit and prevent dam failure due to liquefaction. The liquefaction potential analysis was carried out using a semi-empirical procedure according to Idriss and Boulanger (2006). The analysis was performed under 2 (two) earthquake conditions, namely Operating Basis Earthquake (OBE) and Safety Evaluation Earthquake (SEE), using different values of fines content (5%, 15%, 35%) and earthquake magnitudes (6.8, 7.0, 7.3, 7.5 and 7.7). The analysis shows that the foundation plan of the Budong-Budong Dam has the potential for liquefaction under both OBE and SEE conditions, which generally occurs at a depth of about 10-12 m from the ground surface. The liquefaction potential of finer-grained river deposits tends to be lower

TeknikVol. 46(2)
Diponegoro University (ID)
Climate action
Openalex Percentile: Top 92%
Geotechnical Engineering and Underground Structures
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.