Analysis of Initial Impoundment Using the F.J. Mock Flow Discharge Model at Pamukkulu Dam

The construction of a dam consists of several stages, including construction preparation, construction planning, construction execution, and initial reservoir impoundment. This study aims to determine the duration of the initial impoundment of the Pamukkulu Reservoir during dry, normal, and wet years using the F.J. Mock water availability method. Water losses in this study include reservoir water release through the bottom outlet to meet irrigation water demand at a rate of 0.3 m³/s and reservoir evaporation. The calculation of the impoundment duration is based on the monthly accumulation of volume until reaching the total storage volume of 82.57 million m³ at a normal water level elevation of +126.00 meters. The analysis results indicate that the duration of the initial impoundment of the Pamukkulu Reservoir is 11.16 months (335 days) in a dry year with an inflow reliability of 31.81%, 8.66 months (260 days) in a normal year with an inflow reliability of 63.63%, and 7.63 months (229 days) in a wet year with an inflow reliability of 77.27%. The study concludes that the Pamukkulu Dam will reach its normal water level storage volume in December (first period) during a wet year classification.

Authors

Institutions

Publication Details

Journal
Teknik
Published
2025-04-14
DOI
https://doi.org/10.14710/teknik.v46i2.67500
Citations
1
Primary Topic
Hydraulic flow and structures
Type
article
Field-Weighted Citation Impact
0.95
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Initial Impoundment Using the F.J. Mock Flow Discharge Model at Pamukkulu Dam

Suharyanto Suharyanto, Dyah Ari Wulandari, Hendy Adiyat Nugraha
1 citations
Teknik
Hydraulic flow and structures
0.95
article

Analysis of Initial Impoundment Using the F.J. Mock Flow Discharge Model at Pamukkulu Dam

Suharyanto Suharyanto, Dyah Ari Wulandari, Hendy Adiyat Nugraha
article en
1 citations

Abstract

The construction of a dam consists of several stages, including construction preparation, construction planning, construction execution, and initial reservoir impoundment. This study aims to determine the duration of the initial impoundment of the Pamukkulu Reservoir during dry, normal, and wet years using the F.J. Mock water availability method. Water losses in this study include reservoir water release through the bottom outlet to meet irrigation water demand at a rate of 0.3 m³/s and reservoir evaporation. The calculation of the impoundment duration is based on the monthly accumulation of volume until reaching the total storage volume of 82.57 million m³ at a normal water level elevation of +126.00 meters. The analysis results indicate that the duration of the initial impoundment of the Pamukkulu Reservoir is 11.16 months (335 days) in a dry year with an inflow reliability of 31.81%, 8.66 months (260 days) in a normal year with an inflow reliability of 63.63%, and 7.63 months (229 days) in a wet year with an inflow reliability of 77.27%. The study concludes that the Pamukkulu Dam will reach its normal water level storage volume in December (first period) during a wet year classification.

TeknikVol. 46(2)
Diponegoro University (ID)
Clean water and sanitation
Openalex Percentile: Top 27%
Hydraulic flow and structures
0.95
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.