Analysis of derating necessity of oil-immersed 10/0.4 kV/kV power transformers–the case studies of four PV power plants

In the last few years many PV power plants have been connected to the electric distribution network. They are nonlinear sources of electric power and consequently generate current harmonics. These harmonics cause heating of power transformers due to the additional eddy current and core losses, skin effect, etc. This paper analyzes the necessity of derating power transformers installed at the points of common coupling (PCC) of PV power plants. Calculations are done in accordance with EN 50464-3:2007. Four two-winding three-phase oil-immersed 10/0.4 kV/kV power transformers with rated power equal to 150 kVA (two of them), 250 kVA, and 1250 kVA are analyzed. In all cases, it is presented that there is no need to derating power transformers because analyzed PV inverters generate low current harmonics at medium and high power.

Authors

Institutions

Publication Details

Published
2025-03-19
DOI
https://doi.org/10.1109/infoteh64129.2025.10959179
Primary Topic
Power Transformer Diagnostics and Insulation
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of derating necessity of oil-immersed 10/0.4 kV/kV power transformers–the case studies of four PV power plants

Bojan Erceg, Mladen Banjanin, Marko Rosić, Željko V. Despotović
Power Transformer Diagnostics and Insulation
article

Analysis of derating necessity of oil-immersed 10/0.4 kV/kV power transformers–the case studies of four PV power plants

Bojan Erceg, Mladen Banjanin, Marko Rosić, Željko V. Despotović
article en

Abstract

In the last few years many PV power plants have been connected to the electric distribution network. They are nonlinear sources of electric power and consequently generate current harmonics. These harmonics cause heating of power transformers due to the additional eddy current and core losses, skin effect, etc. This paper analyzes the necessity of derating power transformers installed at the points of common coupling (PCC) of PV power plants. Calculations are done in accordance with EN 50464-3:2007. Four two-winding three-phase oil-immersed 10/0.4 kV/kV power transformers with rated power equal to 150 kVA (two of them), 250 kVA, and 1250 kVA are analyzed. In all cases, it is presented that there is no need to derating power transformers because analyzed PV inverters generate low current harmonics at medium and high power.

Institut Mihajlo Pupin (RS), University of Kragujevac (RS), University of Banja Luka (BA), University of East Sarajevo (BA), University of Belgrade (RS)
Openalex Percentile: Top 94%
Power Transformer Diagnostics and Insulation
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis of derating necessity of oil-immersed 10/0.4 kV/kV power transformers–the case studies of four PV power plants — Bojan Erceg, Mladen Banjanin, et al. · (2025) | TGRS Research Map | TGRS