End of day process optimization through multi-mode resource constrained project scheduling - A banking case study

An End-of-Day process is a batch job that includes a sequence of programs, wherein tasks are completed automatically at times specified by a scheduler. The efficient allocation of resources for the timely execution of tasks allows a company to reduce the overall time needed for the completion of the work and improve customer satisfaction by delivering orders on time. This paper presents a case study of a Turkish bank with the objective of minimizing the duration of the end-of-day process through the optimization of work scheduling and resource allocation. This problem is modeled as a multi-mode resource constrained project scheduling problem, optimally resolved by mixed-integer programming, and approximated via simulated annealing heuristic. The scheduler in this paper can also be used to assess the importance of scheduling and crashing tasks, along with the sufficiency of the infrastructure to optimize the End-of-Day process.

Authors

Publication Details

Journal
An International Journal of Optimization and Control Theories & Applications (IJOCTA)
Published
2025-04-08
DOI
https://doi.org/10.36922/ijocta.1694
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

End of day process optimization through multi-mode resource constrained project scheduling - A banking case study

Ilgar Şafak, Emin Genc, Ezgi Karabulut Türkseven
An International Journal of Optimization and Control Theories & Applications (IJOCTA)
Resource-Constrained Project Scheduling
article

End of day process optimization through multi-mode resource constrained project scheduling - A banking case study

Ilgar Şafak, Emin Genc, Ezgi Karabulut Türkseven
article en

Abstract

An End-of-Day process is a batch job that includes a sequence of programs, wherein tasks are completed automatically at times specified by a scheduler. The efficient allocation of resources for the timely execution of tasks allows a company to reduce the overall time needed for the completion of the work and improve customer satisfaction by delivering orders on time. This paper presents a case study of a Turkish bank with the objective of minimizing the duration of the end-of-day process through the optimization of work scheduling and resource allocation. This problem is modeled as a multi-mode resource constrained project scheduling problem, optimally resolved by mixed-integer programming, and approximated via simulated annealing heuristic. The scheduler in this paper can also be used to assess the importance of scheduling and crashing tasks, along with the sufficiency of the infrastructure to optimize the End-of-Day process.

An International Journal of Optimization and Control Theories & Applications (IJOCTA)Vol. 15(2)
Openalex Percentile: Top 92%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.