Pengaruh Metode Pelaksanaan Terhadap Kinerja Waktu Proyek Rekonstruksi Jembatan di Kota Palu

The bridge reconstruction project is an effort to rebuild bridges that have been destroyed by the earthquake and tsunami that hit Palu City. The implementation of the bridge reconstruction project has complicated work that raises an analysis of the effect of the bridge project implementation method on project time performance. The purpose of this study was to determine the effect of implementation methods on the time performance of the bridge reconstruction project in Palu City. The sample of this study amounted to 22 workers on the bridge reconstruction project using Purposive Sampling method. The field collection process was carried out by collecting primary data in the form of interviews and distributing questionnaires. The data were processed using descriptive statistics and multiple linear regression analysis. The results of this study indicate that partially of the five variabels affecting the implementation method, the material factor variabel has a significant effect on the time performance of the bridge reconstruction project. While simultaneously work methods, labor, material factors, equipment, and project site conditions have an effect of 8,988 with a significant 0.000 on the variabel time performance of the bridge reconstruction project in Palu City.

Authors

Institutions

Publication Details

Journal
REKONSTRUKSI TADULAKO Civil Engineering Journal on Research and Development
Published
2025-03-02
DOI
https://doi.org/10.22487/renstra.v6i1.724
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Pengaruh Metode Pelaksanaan Terhadap Kinerja Waktu Proyek Rekonstruksi Jembatan di Kota Palu

F. Fahirah, T. Hilmansyah, Z. Salsabila
REKONSTRUKSI TADULAKO Civil Engineering Journal on Research and Development
Occupational Health and Safety Management
article

Pengaruh Metode Pelaksanaan Terhadap Kinerja Waktu Proyek Rekonstruksi Jembatan di Kota Palu

F. Fahirah, T. Hilmansyah, Z. Salsabila
article en

Abstract

The bridge reconstruction project is an effort to rebuild bridges that have been destroyed by the earthquake and tsunami that hit Palu City. The implementation of the bridge reconstruction project has complicated work that raises an analysis of the effect of the bridge project implementation method on project time performance. The purpose of this study was to determine the effect of implementation methods on the time performance of the bridge reconstruction project in Palu City. The sample of this study amounted to 22 workers on the bridge reconstruction project using Purposive Sampling method. The field collection process was carried out by collecting primary data in the form of interviews and distributing questionnaires. The data were processed using descriptive statistics and multiple linear regression analysis. The results of this study indicate that partially of the five variabels affecting the implementation method, the material factor variabel has a significant effect on the time performance of the bridge reconstruction project. While simultaneously work methods, labor, material factors, equipment, and project site conditions have an effect of 8,988 with a significant 0.000 on the variabel time performance of the bridge reconstruction project in Palu City.

REKONSTRUKSI TADULAKO Civil Engineering Journal on Research and Development
Tadulako University (ID)
Openalex Percentile: Top 90%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Pengaruh Metode Pelaksanaan Terhadap Kinerja Waktu Proyek Rekonstruksi Jembatan di Kota Palu — F. Fahirah, T. Hilmansyah, et al. · REKONSTRUKSI TADULAKO Civil Engineering Journal on Research and Development (2025) | TGRS Research Map | TGRS