GEOTECHNICAL ENGINEERING DESIGN FOR SETTLEMENT MITIGATION IN THE DEEP FOUNDATION CONSTRUCTION AREA, NORTH SUMATRA PROVINCE, INDONESIA

The construction project in area Y, North Sumatra will be installed with piles as the preliminary foundation for a multi-story building. The installation of these piles resulted in settlement at several boreholes points analyzed using Rocscience Settle3. The settlement ranged from 65 mm - 95 mm at over 11 boreholes over the construction area. This settlement has the potential to cause structural damage to the building, therefore geotechnical engineering is needed as a solution to prevent it. Ground improvement as geotechnical engineering can be done to support the design of safer foundations by increasing soil consistency in shallow to deep layers. Vibro compaction geotechnical engineering reduces the total settlement of the research area from 90 mm to 68 mm in BH-01, BH-04, and BH-06. In boreholes with low bearing capacity and medium settlement values such as BH-1, monitoring using a settlement gauge is required to provide efficient prevention in safe foundation planning without neglecting cost effective concern.

Authors

Publication Details

Journal
Bulletin of Scientific Contribution
Published
2024-12-27
DOI
https://doi.org/10.24198/bsc.v22i3.59032
Primary Topic
Geotechnical and construction materials studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

GEOTECHNICAL ENGINEERING DESIGN FOR SETTLEMENT MITIGATION IN THE DEEP FOUNDATION CONSTRUCTION AREA, NORTH SUMATRA PROVINCE, INDONESIA

Faisal Helmi, Kawthar Muhammad, Raden Irvan Sophian, Hilman Damanhuri
Bulletin of Scientific Contribution
Geotechnical and construction materials studies
article

GEOTECHNICAL ENGINEERING DESIGN FOR SETTLEMENT MITIGATION IN THE DEEP FOUNDATION CONSTRUCTION AREA, NORTH SUMATRA PROVINCE, INDONESIA

Faisal Helmi, Kawthar Muhammad, Raden Irvan Sophian, Hilman Damanhuri
article en

Abstract

The construction project in area Y, North Sumatra will be installed with piles as the preliminary foundation for a multi-story building. The installation of these piles resulted in settlement at several boreholes points analyzed using Rocscience Settle3. The settlement ranged from 65 mm - 95 mm at over 11 boreholes over the construction area. This settlement has the potential to cause structural damage to the building, therefore geotechnical engineering is needed as a solution to prevent it. Ground improvement as geotechnical engineering can be done to support the design of safer foundations by increasing soil consistency in shallow to deep layers. Vibro compaction geotechnical engineering reduces the total settlement of the research area from 90 mm to 68 mm in BH-01, BH-04, and BH-06. In boreholes with low bearing capacity and medium settlement values such as BH-1, monitoring using a settlement gauge is required to provide efficient prevention in safe foundation planning without neglecting cost effective concern.

Bulletin of Scientific ContributionVol. 22(3)
Openalex Percentile: Top 68%
Geotechnical and construction materials studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.