RESEARCH ON THE SETTLEMENT OF BRIDGE APPROACH EMBANKMENTS DURING THE OPERATION PROCESS: A CASE STUDY OF THREE BRIDGES IN TRA VINH PROVINCE, VIETNAM

In the Mekong Delta in general and Tra Vinh Province in particular, the settlement of bridge approach embankments has occurred for many years. However, the current solution to compensate for settlement has not been resolved completely and sustainably. The study was conducted to learn about the nature of the settlement phenomenon and predict the amount of settlement compensation for bridge approach embankments during operation throughout the province. The results show that in the settlement of bridge approach embankments, in the case of not treating the ground, the total settlement is 0.21 m, and the time to stop settlement is 100 years; in thecase of treating the ground, the total settlement is 0.12 m, the time to stop settlement is 50 years. This study helps designers and constructors have solutions to properly treat the bridge approach embankments to avoid the settlement of the bridge approach.

Authors

Institutions

Publication Details

Journal
TRA VINH UNIVERSITY JOURNAL OF SCIENCE
Published
2024-12-13
DOI
https://doi.org/10.35382/tvujs.14.8.2024.108
Primary Topic
Structural Engineering and Vibration Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

RESEARCH ON THE SETTLEMENT OF BRIDGE APPROACH EMBANKMENTS DURING THE OPERATION PROCESS: A CASE STUDY OF THREE BRIDGES IN TRA VINH PROVINCE, VIETNAM

Van Hiep Huynh, Tuan Nguyen Gia, Tri Huu Huynh
TRA VINH UNIVERSITY JOURNAL OF SCIENCE
Structural Engineering and Vibration Analysis
article

RESEARCH ON THE SETTLEMENT OF BRIDGE APPROACH EMBANKMENTS DURING THE OPERATION PROCESS: A CASE STUDY OF THREE BRIDGES IN TRA VINH PROVINCE, VIETNAM

Van Hiep Huynh, Tuan Nguyen Gia, Tri Huu Huynh
article en

Abstract

In the Mekong Delta in general and Tra Vinh Province in particular, the settlement of bridge approach embankments has occurred for many years. However, the current solution to compensate for settlement has not been resolved completely and sustainably. The study was conducted to learn about the nature of the settlement phenomenon and predict the amount of settlement compensation for bridge approach embankments during operation throughout the province. The results show that in the settlement of bridge approach embankments, in the case of not treating the ground, the total settlement is 0.21 m, and the time to stop settlement is 100 years; in thecase of treating the ground, the total settlement is 0.12 m, the time to stop settlement is 50 years. This study helps designers and constructors have solutions to properly treat the bridge approach embankments to avoid the settlement of the bridge approach.

TRA VINH UNIVERSITY JOURNAL OF SCIENCE
Tra Vinh University (VN)
Openalex Percentile: Top 68%
Structural Engineering and Vibration Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.