Impact of Contractor Selection Criteria on Project Delays in Jordanian Public Construction

Delays in public construction projects remain a global challenge, with contractor selection playing a crucial role in mitigating or exacerbating such delays. This study examines the impact of contractor selection criteria on project delays in Jordan’s public construction sector, offering insights applicable to similar contexts. By integrating Multi-Attribute Utility Theory (MAUT) and Analytical Hierarchy Process (AHP), this research develops a structured framework for contractor pre-qualification, enhancing decision-making processes. Using a mixed-method approach, data was collected from 250 industry professionals and two school construction case studies. Findings highlight quality commitment (RI 0.82), cost adherence (RI 0.77), and timely completion (RI 0.824) as key success factors. The study also quantifies the impact of contractor selection on project performance (impact index: 80.6%) and identifies critical prequalification attributes, including technical staff competency (27%), project planning (22%), and financial stability (20%). This research makes a significant contribution by introducing a standardized contractor selection framework that balances cost and quality considerations, addressing a critical gap in existing literature. The findings provide actionable recommendations for policymakers, advocating a shift from lowestbid selection toward a more holistic contractor evaluation to enhance project success

Authors

Publication Details

Journal
Jordan Journal of Civil Engineering
Published
2025-01-01
DOI
https://doi.org/10.14525/jjce.v19i2.07
Citations
1
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.11
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Impact of Contractor Selection Criteria on Project Delays in Jordanian Public Construction

Amireh Farah
1 citations
Jordan Journal of Civil Engineering
Construction Project Management and Performance
2.11
article

Impact of Contractor Selection Criteria on Project Delays in Jordanian Public Construction

Amireh Farah
article en
1 citations

Abstract

Delays in public construction projects remain a global challenge, with contractor selection playing a crucial role in mitigating or exacerbating such delays. This study examines the impact of contractor selection criteria on project delays in Jordan’s public construction sector, offering insights applicable to similar contexts. By integrating Multi-Attribute Utility Theory (MAUT) and Analytical Hierarchy Process (AHP), this research develops a structured framework for contractor pre-qualification, enhancing decision-making processes. Using a mixed-method approach, data was collected from 250 industry professionals and two school construction case studies. Findings highlight quality commitment (RI 0.82), cost adherence (RI 0.77), and timely completion (RI 0.824) as key success factors. The study also quantifies the impact of contractor selection on project performance (impact index: 80.6%) and identifies critical prequalification attributes, including technical staff competency (27%), project planning (22%), and financial stability (20%). This research makes a significant contribution by introducing a standardized contractor selection framework that balances cost and quality considerations, addressing a critical gap in existing literature. The findings provide actionable recommendations for policymakers, advocating a shift from lowestbid selection toward a more holistic contractor evaluation to enhance project success

Jordan Journal of Civil EngineeringVol. 19(2)
Openalex Percentile: Top 15%
Construction Project Management and Performance
2.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.