Construction control of cable-stayed bridge top push method based on BIM technology

This research focuses on enhancing the precision and management of the top push method in cable-stayed bridge construction through the application of building information modeling (BIM) technology. By evaluating BIM standards, engineering decomposition standards, and modeling software, an appropriate BIM platform and standard were selected to create BIM models for each component of cable-stayed bridges. Using the Yellow River Cable-stayed Bridge as a case study, various construction schemes were visualized through BIM. The study investigated the impact of key structural parameters, such as cable stiffness, main girder stiffness, and main tower stiffness, on the top push method by adjusting them by − 3%, − 1%, 1%, and 3%. The outcomes showed that changes in cable stiffness had the most significant effect, with a 1% stiffness variation causing a 51.3 mm displacement in the main girder and a 124.2 kN deviation in cable force, increasing to 151.2 mm and 179.8 kN respectively for a 3% change. This research demonstrates that BIM technology can significantly improve the management of top-push construction methods, enable three-dimensional visualization of the construction process, and advance the informatization and industrialization of bridge construction.

Authors

Institutions

Publication Details

Journal
Discover Applied Sciences
Published
2025-04-12
DOI
https://doi.org/10.1007/s42452-025-06764-1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Construction control of cable-stayed bridge top push method based on BIM technology

Wenming Su, Yongquan Dong, Wenqiang Dou, Chengyong Chen et al.
Discover Applied Sciences
BIM and Construction Integration
article

Construction control of cable-stayed bridge top push method based on BIM technology

Wenming Su, Yongquan Dong, Wenqiang Dou, Chengyong Chen, Ben Zhang
article en

Abstract

This research focuses on enhancing the precision and management of the top push method in cable-stayed bridge construction through the application of building information modeling (BIM) technology. By evaluating BIM standards, engineering decomposition standards, and modeling software, an appropriate BIM platform and standard were selected to create BIM models for each component of cable-stayed bridges. Using the Yellow River Cable-stayed Bridge as a case study, various construction schemes were visualized through BIM. The study investigated the impact of key structural parameters, such as cable stiffness, main girder stiffness, and main tower stiffness, on the top push method by adjusting them by − 3%, − 1%, 1%, and 3%. The outcomes showed that changes in cable stiffness had the most significant effect, with a 1% stiffness variation causing a 51.3 mm displacement in the main girder and a 124.2 kN deviation in cable force, increasing to 151.2 mm and 179.8 kN respectively for a 3% change. This research demonstrates that BIM technology can significantly improve the management of top-push construction methods, enable three-dimensional visualization of the construction process, and advance the informatization and industrialization of bridge construction.

Discover Applied SciencesVol. 7(4)
Luye Pharma (China) (CN), Shandong Institute for Product Quality Inspection (CN)
U.S. Department of Transportation
Openalex Percentile: Top 93%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Construction control of cable-stayed bridge top push method based on BIM technology — Wenming Su, Yongquan Dong, et al. · Discover Applied Sciences (2025) | TGRS Research Map | TGRS