Resource Utilization and Repetitive Construction Scheduling using the Discrete Event Simulation Method

The efficient utilization of resources in repetitive construction projects is crucial to optimizing schedules and reducing costs. This study investigates the application of Discrete Event Simulation (DES) to enhance resource utilization in scheduling repetitive construction activities, specifically the construction of Type-36 houses in Palu City, Indonesia. Traditional project-based planning methods, such as the Critical Path Method (CPM), are compared with production-based planning approaches. The study shows that although CPM can effectively determine project completion times, it falls short in optimizing resource allocation, particularly in scenarios involving repetitive tasks. By employing the DES tool SIMUL8, the study models the construction process and simulates various resource allocation scenarios to identify the optimal resources required. The results indicate that DES provides a more dynamic and accurate analysis, allowing real-time adjustments and improved resource management. The study concludes that integrating DES into construction project management can significantly enhance efficiency, reduce project duration, and optimize resource utilization.

Authors

Publication Details

Journal
Engineering Technology & Applied Science Research
Published
2025-04-03
DOI
https://doi.org/10.48084/etasr.9795
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Resource Utilization and Repetitive Construction Scheduling using the Discrete Event Simulation Method

Arief Setiawan, Amar Akbar Ali, Adnan Fadjar
Engineering Technology & Applied Science Research
BIM and Construction Integration
article

Resource Utilization and Repetitive Construction Scheduling using the Discrete Event Simulation Method

Arief Setiawan, Amar Akbar Ali, Adnan Fadjar
article en

Abstract

The efficient utilization of resources in repetitive construction projects is crucial to optimizing schedules and reducing costs. This study investigates the application of Discrete Event Simulation (DES) to enhance resource utilization in scheduling repetitive construction activities, specifically the construction of Type-36 houses in Palu City, Indonesia. Traditional project-based planning methods, such as the Critical Path Method (CPM), are compared with production-based planning approaches. The study shows that although CPM can effectively determine project completion times, it falls short in optimizing resource allocation, particularly in scenarios involving repetitive tasks. By employing the DES tool SIMUL8, the study models the construction process and simulates various resource allocation scenarios to identify the optimal resources required. The results indicate that DES provides a more dynamic and accurate analysis, allowing real-time adjustments and improved resource management. The study concludes that integrating DES into construction project management can significantly enhance efficiency, reduce project duration, and optimize resource utilization.

Engineering Technology & Applied Science ResearchVol. 15(2)
Openalex Percentile: Top 94%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.