Study on the impact of partial unloading on the structural deformation of prefabricated segmental subway tunnels

To address the issue of deformation in prefabricated segmental subway tunnels caused by partial excavation unloading which affects the safety of subway operational safety. In this article, the subway tunnel of Zhengzhou metro, which partial unloading due to pit excavation on the underground expressway reconstruction project, was taken as an example to study this issue. First, the mechanism of partial unloading of upper bar pit excavation on the mechanical response of lower existing tunnel structure was investigated. Then, a three-dimensional finite element model was developed to simulate the interaction between the excavation pit and the tunnel. The influence of partial unloading caused by strip foundation pit excavation on the mechanical response and deformation characteristics of underlying existing tunnel segment structures were analyzed. Finally, the reinforcement effects of tunnel deformation control measures were compared, and the optimal solution to control tunnel deformation affected by partial excavation and unloading was proposed. Results indicate that the tunnel structure mainly produces overall uneven uplift, which is affected by the partial unloading of the upper bar pit excavation. The vertical displacement at the top of the tunnel is the largest, the vertical displacement near the centerline of the pit is significant, and the maximum vertical displacement usually occurs at the joints. The force of bolts generated in the prefabricated segment structure under partial unloading conditions was tensile force, which was related to the variation trend of the segment joints and the magnitude of the bending moment at the joint locations. After comparing the different methods, portal reinforcement and counterpressure can significantly control deformation generated by partial unloading.

Authors

Institutions

Publication Details

Journal
Scientific Reports
Published
2025-04-01
DOI
https://doi.org/10.1038/s41598-025-95900-3
Citations
1
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
0.95
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Study on the impact of partial unloading on the structural deformation of prefabricated segmental subway tunnels

Hongzhi Zou, Teng‐Fei Li, Lingling Zhao, Hao Li et al.
1 citations
Scientific Reports
Geotechnical Engineering and Underground Structures
0.95
article

Study on the impact of partial unloading on the structural deformation of prefabricated segmental subway tunnels

Hongzhi Zou, Teng‐Fei Li, Lingling Zhao, Hao Li, Yuancheng Guo
article en
1 citations

Abstract

To address the issue of deformation in prefabricated segmental subway tunnels caused by partial excavation unloading which affects the safety of subway operational safety. In this article, the subway tunnel of Zhengzhou metro, which partial unloading due to pit excavation on the underground expressway reconstruction project, was taken as an example to study this issue. First, the mechanism of partial unloading of upper bar pit excavation on the mechanical response of lower existing tunnel structure was investigated. Then, a three-dimensional finite element model was developed to simulate the interaction between the excavation pit and the tunnel. The influence of partial unloading caused by strip foundation pit excavation on the mechanical response and deformation characteristics of underlying existing tunnel segment structures were analyzed. Finally, the reinforcement effects of tunnel deformation control measures were compared, and the optimal solution to control tunnel deformation affected by partial excavation and unloading was proposed. Results indicate that the tunnel structure mainly produces overall uneven uplift, which is affected by the partial unloading of the upper bar pit excavation. The vertical displacement at the top of the tunnel is the largest, the vertical displacement near the centerline of the pit is significant, and the maximum vertical displacement usually occurs at the joints. The force of bolts generated in the prefabricated segment structure under partial unloading conditions was tensile force, which was related to the variation trend of the segment joints and the magnitude of the bending moment at the joint locations. After comparing the different methods, portal reinforcement and counterpressure can significantly control deformation generated by partial unloading.

Scientific ReportsVol. 15(1)
Zhengzhou University (CN)
Sustainable cities and communities
Openalex Percentile: Top 27%
Geotechnical Engineering and Underground Structures
0.95
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.