Analyzing Stability of Estimates at Completion for Long Duration Development Efforts
The article provides empirical evidence that long duration programs behave differently than short duration programs. Program managers are cautioned to consider the length of duration when estimating cost at completion up to and slightly beyond the 70% completion point