Minimizing Makespan in Three Phase Flowshop Scheduling Problems with Multiple Processor at Level First

This paper indicates the investigation of most efficient use of limited resources in production industries. Here the study provides a sequence of steps for solving the problems with three phase flowshop scheduling with equi-potential machines with the processing time accepted as Triangular Fuzzy numbers, with each machine having different operating cost. Objectives: The motivation behind this study is to find ideal or near ideal solution for solving the three-stage scheduling problem in fuzzy environment and making the best or most effective use of time and money. Methods: Here the methodology Branch and Bound is stacked up with the Genetic algorithm and Gupta’s heuristic method. In our study we evaluated the technique of finding step by step process for solving the three-stage scheduling problem with processing time accepted as triangular fuzzy number at each stage . Various parameters like transportation time in between machines, no-idle time, job block etc. can be extended work for this study. Conclusion: In this study the point that should be observed that the Branch and Bound gave the makespan 139 but on the other hand by genetic algorithm the make span is different according to different iteration . It may happen that by chance, at any one iteration genetic algorithm gives more optimum solution ,but this will not possible always. Also, Gupta’s Heuristic does not guarantee the optimum solution but prioritizes jobs based on the balanced between stages .This is useful when there is no need to minimum makespan but ensuring a smooth flow across the multiple stages.

Authors

Publication Details

Journal
Communications on Applied Nonlinear Analysis
Published
2025-03-25
DOI
https://doi.org/10.52783/cana.v32.4454
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Minimizing Makespan in Three Phase Flowshop Scheduling Problems with Multiple Processor at Level First

N.A. Sonia
Communications on Applied Nonlinear Analysis
Scheduling and Optimization Algorithms
article

Minimizing Makespan in Three Phase Flowshop Scheduling Problems with Multiple Processor at Level First

N.A. Sonia
article en

Abstract

This paper indicates the investigation of most efficient use of limited resources in production industries. Here the study provides a sequence of steps for solving the problems with three phase flowshop scheduling with equi-potential machines with the processing time accepted as Triangular Fuzzy numbers, with each machine having different operating cost. Objectives: The motivation behind this study is to find ideal or near ideal solution for solving the three-stage scheduling problem in fuzzy environment and making the best or most effective use of time and money. Methods: Here the methodology Branch and Bound is stacked up with the Genetic algorithm and Gupta’s heuristic method. In our study we evaluated the technique of finding step by step process for solving the three-stage scheduling problem with processing time accepted as triangular fuzzy number at each stage . Various parameters like transportation time in between machines, no-idle time, job block etc. can be extended work for this study. Conclusion: In this study the point that should be observed that the Branch and Bound gave the makespan 139 but on the other hand by genetic algorithm the make span is different according to different iteration . It may happen that by chance, at any one iteration genetic algorithm gives more optimum solution ,but this will not possible always. Also, Gupta’s Heuristic does not guarantee the optimum solution but prioritizes jobs based on the balanced between stages .This is useful when there is no need to minimum makespan but ensuring a smooth flow across the multiple stages.

Communications on Applied Nonlinear AnalysisVol. 32(9s)
Openalex Percentile: Top 92%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Minimizing Makespan in Three Phase Flowshop Scheduling Problems with Multiple Processor at Level First — N.A. Sonia · Communications on Applied Nonlinear Analysis (2025) | TGRS Research Map | TGRS