Monitoring of bottom strains during impoundment and operation of a large-scale experimental dam

Strains at the bottom of a large-scale experimental embankment dam were measured by fibre optics. The strains were measured in four sections, orthogonal to the dam axis. The fibre optic set up was operational after finalising the dam construction. The measurements were conducted continuously during the impoundment and later during the operation with an upstream water level of a maximum of 3.5 m. Based on the measurements, the post-construction behaviour of the dam was observed, indicating settlements. The foundation of the dam is inclined, which was captured by the measurements, with indications of more shear stresses developing at the downstream side. Variations of strains in the different dam zones were observed. The impoundment is causing most of the strain development in the dam. The strains develop further over time after the reservoir is at its maximum level, indicating a transient process is in place.

Authors

Institutions

Publication Details

Journal
International Journal of Physical Modelling in Geotechnics
Published
2025-04-01
DOI
https://doi.org/10.1680/jphmg.24.00028
Citations
1
Primary Topic
Dam Engineering and Safety
Type
article
Field-Weighted Citation Impact
0.95
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Monitoring of bottom strains during impoundment and operation of a large-scale experimental dam

Jan Laue, Peter Viklander, Jasmina Toromanovic, Sven Knutsson et al.
1 citations
International Journal of Physical Modelling in Geotechnics
Dam Engineering and Safety
0.95
article

Monitoring of bottom strains during impoundment and operation of a large-scale experimental dam

Jan Laue, Peter Viklander, Jasmina Toromanovic, Sven Knutsson, Hans Mattsson
article en
1 citations

Abstract

Strains at the bottom of a large-scale experimental embankment dam were measured by fibre optics. The strains were measured in four sections, orthogonal to the dam axis. The fibre optic set up was operational after finalising the dam construction. The measurements were conducted continuously during the impoundment and later during the operation with an upstream water level of a maximum of 3.5 m. Based on the measurements, the post-construction behaviour of the dam was observed, indicating settlements. The foundation of the dam is inclined, which was captured by the measurements, with indications of more shear stresses developing at the downstream side. Variations of strains in the different dam zones were observed. The impoundment is causing most of the strain development in the dam. The strains develop further over time after the reservoir is at its maximum level, indicating a transient process is in place.

International Journal of Physical Modelling in GeotechnicsVol. 25(4)
Luleå University of Technology (SE), Norsk Hydro (Sweden) (SE)
Openalex Percentile: Top 27%
Dam Engineering and Safety
0.95
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.