From promise to practice. A landscape perspective on discrepancies between permit documentation and built solar power plants

Over the past years, the implementation of solar energy technology in the landscape has increased significantly. Landscape quality, an objective for solar power plant (SPP) development in the Netherlands, is therein potentially compromised. In this study, we examine the discrepancies of five Dutch SPPs through post-occupancy evaluation and structured interviews. We found 79 discrepancies in spatial measures. Interviewees attributed discrepancies to the business case, permit procedures, regulation, enforcement, and maintenance. We make two recommendations to improve policy and simultaneously strengthen the mandate of landscape planning and design with regard to SPP development. First, broader societal concerns need to be better defined as permit requirements to prioritise them in SPP development. Secondly, design visualisations by landscape architects need to consider temporal aspects to foster communication and transparency among stakeholders. These changes in policy and SPP development practice are needed to maintain landscape quality as stipulated for example, by the European Landscape Convention.

Authors

Institutions

Publication Details

Journal
Landscape Research
Published
2025-03-31
DOI
https://doi.org/10.1080/01426397.2025.2475170
Citations
1
Primary Topic
Social Acceptance of Renewable Energy
Type
article
Field-Weighted Citation Impact
4.20
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

From promise to practice. A landscape perspective on discrepancies between permit documentation and built solar power plants

Merel Enserink, Dirk Oudes, Sven Stremke, Vincent Klaaskate
1 citations
Landscape Research
Social Acceptance of Renewable Energy
4.20
article

From promise to practice. A landscape perspective on discrepancies between permit documentation and built solar power plants

Merel Enserink, Dirk Oudes, Sven Stremke, Vincent Klaaskate
article en
1 citations

Abstract

Over the past years, the implementation of solar energy technology in the landscape has increased significantly. Landscape quality, an objective for solar power plant (SPP) development in the Netherlands, is therein potentially compromised. In this study, we examine the discrepancies of five Dutch SPPs through post-occupancy evaluation and structured interviews. We found 79 discrepancies in spatial measures. Interviewees attributed discrepancies to the business case, permit procedures, regulation, enforcement, and maintenance. We make two recommendations to improve policy and simultaneously strengthen the mandate of landscape planning and design with regard to SPP development. First, broader societal concerns need to be better defined as permit requirements to prioritise them in SPP development. Secondly, design visualisations by landscape architects need to consider temporal aspects to foster communication and transparency among stakeholders. These changes in policy and SPP development practice are needed to maintain landscape quality as stipulated for example, by the European Landscape Convention.

Landscape ResearchVol. 50(6)
Wageningen University & Research (NL)
Openalex Percentile: Top 9%
Social Acceptance of Renewable Energy
4.20
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.