A Disturbance Dynamic Evaluation Method for Steelmaking-continuous Casting Scheduling Based on Converter Processing Time Prediction and Disturbance Influence Process Analysis

Converter completion time delay caused by uncertain events is one of the most frequent disturbances in the steelmaking-continuous casting process (SCCP) with a significant negative impact on the SCCP scheduling. Existing rescheduling methods fall short in providing a comprehensive analysis and evaluation for the production status and disturbance levels, resulting in the scheduling scheme with limited adaptability to on-site environments. This paper addresses this challenge by proposing a dynamic evaluation method for converter scheduling disturbance based on processing time prediction and disturbance influence process analysis. The proposed method consists of three steps that solve the disturbance evaluation problem by predicting the converter processing time, analysing the delay impact of the converter completion time, and solving the real-time procedure buffer capacity. This enables the dynamic scheduling of the SCCP to accurately judge the current operating rhythm and production status, and to achieve precise decision-making for scheduling. Computational experiments based on the actual case from the Chinese steelmaking plants demonstrate the accuracy and effectiveness of the proposed method in large-scale SCCP dynamic scheduling processes. Compared with other methods, the proposed method can effectively reduce the number of rescheduling in production and the deviation of the production process from the initial scheduling scheme by reasonably selecting the scheduling repair strategy, which improves the adaptability of the scheduling scheme to the actual production environment.

Authors

Institutions

Publication Details

Journal
ISIJ International
Published
2025-03-30
DOI
https://doi.org/10.2355/isijinternational.isijint-2024-178
Citations
1
Primary Topic
Metallurgical Processes and Thermodynamics
Type
article
Field-Weighted Citation Impact
0.71

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Disturbance Dynamic Evaluation Method for Steelmaking-continuous Casting Scheduling Based on Converter Processing Time Prediction and Disturbance Influence Process Analysis

Qing Liu, Bailin Wang, Tieke Li, Xin Shao et al.
1 citations
ISIJ International
Metallurgical Processes and Thermodynamics
0.71
article

A Disturbance Dynamic Evaluation Method for Steelmaking-continuous Casting Scheduling Based on Converter Processing Time Prediction and Disturbance Influence Process Analysis

Qing Liu, Bailin Wang, Tieke Li, Xin Shao, Jiangshan Zhang
article en
1 citations

Abstract

Converter completion time delay caused by uncertain events is one of the most frequent disturbances in the steelmaking-continuous casting process (SCCP) with a significant negative impact on the SCCP scheduling. Existing rescheduling methods fall short in providing a comprehensive analysis and evaluation for the production status and disturbance levels, resulting in the scheduling scheme with limited adaptability to on-site environments. This paper addresses this challenge by proposing a dynamic evaluation method for converter scheduling disturbance based on processing time prediction and disturbance influence process analysis. The proposed method consists of three steps that solve the disturbance evaluation problem by predicting the converter processing time, analysing the delay impact of the converter completion time, and solving the real-time procedure buffer capacity. This enables the dynamic scheduling of the SCCP to accurately judge the current operating rhythm and production status, and to achieve precise decision-making for scheduling. Computational experiments based on the actual case from the Chinese steelmaking plants demonstrate the accuracy and effectiveness of the proposed method in large-scale SCCP dynamic scheduling processes. Compared with other methods, the proposed method can effectively reduce the number of rescheduling in production and the deviation of the production process from the initial scheduling scheme by reasonably selecting the scheduling repair strategy, which improves the adaptability of the scheduling scheme to the actual production environment.

ISIJ InternationalVol. 65(5)
University of Science and Technology Beijing (CN)
National Natural Science Foundation of China, University of Science and Technology Beijing, State Key Laboratory of Advanced Metallurgy
Openalex Percentile: Top 34%
Metallurgical Processes and Thermodynamics
0.71
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.