Duration forecasting in resource constrained projects: A hybrid risk model combining complexity indicators with sensitivity measures

This study combines complexity measures from the project scheduling literature and sensitivity measures from the risk analysis literature to improve project duration forecasts in resource constrained projects. A hybrid risk model is proposed incorporating project network measures, resource-related indicators, and risk sensitivity metrics. The hybrid risk model is then used for forecasting the duration of unseen projects. The study contributes to the existing literature by integrating newly proposed activity sensitivity metrics and network and resource related indicators in project forecasting. Additionally, it conducts a large-scale experiment to compare the accuracy of the hybrid risk model against benchmark methods, including Monte Carlo simulations and relevant machine learning algorithms. The results show that inclusion of resource-related variables within the hybrid risk model significantly improves the accuracy, validating recently proposed metrics. The hybrid risk model outperforms most of the benchmark methods in high-uncertainty projects, emphasizing the importance of accurately estimating the flexibility in activity start times. Furthermore, the hybrid risk model of this paper is particularly effective for parallel projects, demonstrating a better performance under various uncertainty and flexibility conditions. Finally, the results are validated using empirical project data. • A new risk model integrates resource-specific characteristics for duration forecasting. • The new model outperforms the previous version that ignores resource limitations. • The new model outperforms the benchmark methods for uncertain and parallel projects. • The new model performs better with limited exibility in start times during training. • The new model is validated with empirical project data for real-world applicability.

Authors

Institutions

Publication Details

Journal
European Journal of Operational Research
Published
2025-03-29
DOI
https://doi.org/10.1016/j.ejor.2025.03.012
Citations
1
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
2.11
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Duration forecasting in resource constrained projects: A hybrid risk model combining complexity indicators with sensitivity measures

İzel Ünsal Altuncan, Mario Vanhoucke
1 citations
European Journal of Operational Research
Resource-Constrained Project Scheduling
2.11
article

Duration forecasting in resource constrained projects: A hybrid risk model combining complexity indicators with sensitivity measures

İzel Ünsal Altuncan, Mario Vanhoucke
article en
1 citations

Abstract

This study combines complexity measures from the project scheduling literature and sensitivity measures from the risk analysis literature to improve project duration forecasts in resource constrained projects. A hybrid risk model is proposed incorporating project network measures, resource-related indicators, and risk sensitivity metrics. The hybrid risk model is then used for forecasting the duration of unseen projects. The study contributes to the existing literature by integrating newly proposed activity sensitivity metrics and network and resource related indicators in project forecasting. Additionally, it conducts a large-scale experiment to compare the accuracy of the hybrid risk model against benchmark methods, including Monte Carlo simulations and relevant machine learning algorithms. The results show that inclusion of resource-related variables within the hybrid risk model significantly improves the accuracy, validating recently proposed metrics. The hybrid risk model outperforms most of the benchmark methods in high-uncertainty projects, emphasizing the importance of accurately estimating the flexibility in activity start times. Furthermore, the hybrid risk model of this paper is particularly effective for parallel projects, demonstrating a better performance under various uncertainty and flexibility conditions. Finally, the results are validated using empirical project data. • A new risk model integrates resource-specific characteristics for duration forecasting. • The new model outperforms the previous version that ignores resource limitations. • The new model outperforms the benchmark methods for uncertain and parallel projects. • The new model performs better with limited exibility in start times during training. • The new model is validated with empirical project data for real-world applicability.

European Journal of Operational ResearchVol. 325(2)
Ghent University (BE), Vlerick Business School (BE), University College London (GB)
Decent work and economic growth
Openalex Percentile: Top 15%
Resource-Constrained Project Scheduling
2.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.