Optimal time-based and cost-based contracts in construction projects under asymmetric information

A project owner (principal) delegates a project to a contractor (agent). Because the contractor has construction experience, he has private information about the project’s expected completion time. Besides, the contractor can exert an unobservable effort to shorten the completion time. Under an asymmetric information setting, we provide the optimal time-based contract and the optimal cost-based contract, both of which consists of one payment scheme. Additionally, we consider a menu of time-based contracts that consists of a series of contracts. By comparing three contracts, we demonstrate that the owner has a preference for the menu of time-based contracts over the other two. The pooling time-based contract is superior to the pooling cost-based contract. We also find that the social welfare under the pooling time-based contract is lower than under the menu of time-based contracts if the daily operating cost is low but it may be higher than under the menu of time-based contracts if the daily operating cost is high. For the pooling cost-based contract, whether it is better than the previous two contracts depend greatly on the proportion of cost borne by the contractor and the daily operating cost.

Authors

Institutions

Publication Details

Journal
Journal of Civil Engineering and Management
Published
2025-03-27
DOI
https://doi.org/10.3846/jcem.2025.23318
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimal time-based and cost-based contracts in construction projects under asymmetric information

Jingru Tong, Zhiyuan Chen, Guanqun Shi, Yichen Wang
Journal of Civil Engineering and Management
Construction Project Management and Performance
article

Optimal time-based and cost-based contracts in construction projects under asymmetric information

Jingru Tong, Zhiyuan Chen, Guanqun Shi, Yichen Wang
article en

Abstract

A project owner (principal) delegates a project to a contractor (agent). Because the contractor has construction experience, he has private information about the project’s expected completion time. Besides, the contractor can exert an unobservable effort to shorten the completion time. Under an asymmetric information setting, we provide the optimal time-based contract and the optimal cost-based contract, both of which consists of one payment scheme. Additionally, we consider a menu of time-based contracts that consists of a series of contracts. By comparing three contracts, we demonstrate that the owner has a preference for the menu of time-based contracts over the other two. The pooling time-based contract is superior to the pooling cost-based contract. We also find that the social welfare under the pooling time-based contract is lower than under the menu of time-based contracts if the daily operating cost is low but it may be higher than under the menu of time-based contracts if the daily operating cost is high. For the pooling cost-based contract, whether it is better than the previous two contracts depend greatly on the proportion of cost borne by the contractor and the daily operating cost.

Journal of Civil Engineering and ManagementVol. 31(4)
Tongji University (CN), Wuhan University (CN), Shanghai Tongji Urban Planning and Design Institute (CN), Huazhong University of Science and Technology (CN)
Openalex Percentile: Top 93%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Optimal time-based and cost-based contracts in construction projects under asymmetric information — Jingru Tong, Zhiyuan Chen, et al. · Journal of Civil Engineering and Management (2025) | TGRS Research Map | TGRS