Exploring risk factors causing delays in mega project in Gulf region: an industrial qualitative approach

Purpose The aim of this study is to investigate and offer varied insights into the risk factors contributing to delays in mega construction projects in the Gulf region by understanding the region’s unique nature and addressing the gaps in the existing regional risk landscape. Design/methodology/approach Firstly, conducting a comprehensive review of previous literature from 2018 to 2023 to examine the unique risk landscape in the Gulf Cooperation Council (GCC). Secondly, applying a Qualitative approach, data were collected by conducting semi-structured interviews with 25 experts who were carefully selected based on their extensive experience and engagement in construction projects in the Gulf, focusing on questions related to the risk factors causing delays in mega construction projects in the region. Lastly, data analysis by employing thematic analysis to extract patterns and themes from the collected data. Findings The analysis unveiled 6 main themes and 12 sub-themes, encompassing 140 risk factors. Of these, 54 risk factors, accounting for almost 38% of the identified risk factors, were newly identified, filling the gap in the GCC risk landscape. These risk factors include the absence of 3D modelling/Building Information Modelling (BIM), issues associated with the testing and commissioning process, and deficiencies in developing a Project Management Information System. Originality/value The study differs from previous research in three keyways. Firstly, the previous papers just list the risk factors without providing any clarifications or causes of these risk factors, while this study, with the utilisation of the thematic analysis, offers deep insights into the risk factors and provides a comprehensive understanding of the causes and impacts of each risk factor as shown in the findings section and Appendix I. Secondly, the previous studies didn’t consider the project phases in categorising the risk factors, while this study categorising the risk factors into six groups that represent the elaboration of the project from the commencement to the testing and commissioning, which allows the stakeholders to focus on ensuring the success of each phase. Thirdly, the study introduces 40 new risk factors, thereby making a novel contribution to the existing body of literature on construction project delays in the Gulf region, addressing the gaps in the regional risk landscape and the evolution of the construction industry.

Authors

Institutions

Publication Details

Journal
Smart and Sustainable Built Environment
Published
2025-03-26
DOI
https://doi.org/10.1108/sasbe-10-2024-0419
Citations
5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
10.53
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Exploring risk factors causing delays in mega project in Gulf region: an industrial qualitative approach

Tara Brooks, Faris Elghaish, Mahmoud Mohamed Nasr Abdou Elshamy
5 citations
Smart and Sustainable Built Environment
Construction Project Management and Performance
10.53
article

Exploring risk factors causing delays in mega project in Gulf region: an industrial qualitative approach

Tara Brooks, Faris Elghaish, Mahmoud Mohamed Nasr Abdou Elshamy
article en
5 citations

Abstract

Purpose The aim of this study is to investigate and offer varied insights into the risk factors contributing to delays in mega construction projects in the Gulf region by understanding the region’s unique nature and addressing the gaps in the existing regional risk landscape. Design/methodology/approach Firstly, conducting a comprehensive review of previous literature from 2018 to 2023 to examine the unique risk landscape in the Gulf Cooperation Council (GCC). Secondly, applying a Qualitative approach, data were collected by conducting semi-structured interviews with 25 experts who were carefully selected based on their extensive experience and engagement in construction projects in the Gulf, focusing on questions related to the risk factors causing delays in mega construction projects in the region. Lastly, data analysis by employing thematic analysis to extract patterns and themes from the collected data. Findings The analysis unveiled 6 main themes and 12 sub-themes, encompassing 140 risk factors. Of these, 54 risk factors, accounting for almost 38% of the identified risk factors, were newly identified, filling the gap in the GCC risk landscape. These risk factors include the absence of 3D modelling/Building Information Modelling (BIM), issues associated with the testing and commissioning process, and deficiencies in developing a Project Management Information System. Originality/value The study differs from previous research in three keyways. Firstly, the previous papers just list the risk factors without providing any clarifications or causes of these risk factors, while this study, with the utilisation of the thematic analysis, offers deep insights into the risk factors and provides a comprehensive understanding of the causes and impacts of each risk factor as shown in the findings section and Appendix I. Secondly, the previous studies didn’t consider the project phases in categorising the risk factors, while this study categorising the risk factors into six groups that represent the elaboration of the project from the commencement to the testing and commissioning, which allows the stakeholders to focus on ensuring the success of each phase. Thirdly, the study introduces 40 new risk factors, thereby making a novel contribution to the existing body of literature on construction project delays in the Gulf region, addressing the gaps in the regional risk landscape and the evolution of the construction industry.

Smart and Sustainable Built Environment
Queen's University Belfast (GB)
Openalex Percentile: Top 2%
Construction Project Management and Performance
10.53
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.