Risk-based completion cost prediction approach in construction projects utilizing machine learning

The construction industry is among the sectors exposed to frequent budget overruns. Therefore, accurately predicting costs to complete the construction projects is a vital point. Several research studies focus on cost estimation, construction risk factors, and their cost impact. Although they produced valuable prediction models for the completion cost of the projects, most of them mainly concentrated on the early stages of the construction. Limited studies produced approaches for completion cost estimation in the execution phase of the projects. Nevertheless, they do not implement total risk score effects in their models. Additional research is necessary to investigate risk-based completion cost prediction throughout the execution phase of construction. The main objective of this study is to provide an approach for the total risk score based completion cost prediction by using machine learning techniques without imposing excessive work. The proposed approach can be utilized at any point during the execution phase of a project to assess the impact of changes in total risk scores on completion costs. Furthermore, predicting the total completion cost using the total risk score simplifies the calculation and procedure rather than depending on breakdowns. To achieve this objective, a machine learning prediction approach was proposed to predict total completion cost based on total risk scores in construction projects. The proposed approach is applied to real-world cases to evaluate the accuracy of completion cost prediction based on risk scores using data from an international construction company. A total of 119 risk and cost data points from 11 projects were analyzed. Six prediction algorithms were employed, utilizing machine learning. Based on the outputs, it was determined that polynomial regression produced the most accurate predictions for available data. This research contributes to enhancing construction organizations' knowledge and planning capacities by quickly predicting project completion costs based on dynamic total risk scores at any time throughout the execution phase of the project.

Authors

Publication Details

Journal
Journal of Information Technology in Construction
Published
2025-03-25
DOI
https://doi.org/10.36680/j.itcon.2025.016
Citations
4
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
8.43
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk-based completion cost prediction approach in construction projects utilizing machine learning

Gül Polat, Aynur Hurriyet Turkyilmaz
4 citations
Journal of Information Technology in Construction
Construction Project Management and Performance
8.43
article

Risk-based completion cost prediction approach in construction projects utilizing machine learning

Gül Polat, Aynur Hurriyet Turkyilmaz
article en
4 citations

Abstract

The construction industry is among the sectors exposed to frequent budget overruns. Therefore, accurately predicting costs to complete the construction projects is a vital point. Several research studies focus on cost estimation, construction risk factors, and their cost impact. Although they produced valuable prediction models for the completion cost of the projects, most of them mainly concentrated on the early stages of the construction. Limited studies produced approaches for completion cost estimation in the execution phase of the projects. Nevertheless, they do not implement total risk score effects in their models. Additional research is necessary to investigate risk-based completion cost prediction throughout the execution phase of construction. The main objective of this study is to provide an approach for the total risk score based completion cost prediction by using machine learning techniques without imposing excessive work. The proposed approach can be utilized at any point during the execution phase of a project to assess the impact of changes in total risk scores on completion costs. Furthermore, predicting the total completion cost using the total risk score simplifies the calculation and procedure rather than depending on breakdowns. To achieve this objective, a machine learning prediction approach was proposed to predict total completion cost based on total risk scores in construction projects. The proposed approach is applied to real-world cases to evaluate the accuracy of completion cost prediction based on risk scores using data from an international construction company. A total of 119 risk and cost data points from 11 projects were analyzed. Six prediction algorithms were employed, utilizing machine learning. Based on the outputs, it was determined that polynomial regression produced the most accurate predictions for available data. This research contributes to enhancing construction organizations' knowledge and planning capacities by quickly predicting project completion costs based on dynamic total risk scores at any time throughout the execution phase of the project.

Journal of Information Technology in ConstructionVol. 30
Openalex Percentile: Top 3%
Construction Project Management and Performance
8.43
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Risk-based completion cost prediction approach in construction projects utilizing machine learning — Gül Polat, Aynur Hurriyet Turkyilmaz · Journal of Information Technology in Construction (2025) | TGRS Research Map | TGRS