Underpinning the Salt Lake Temple

The Salt Lake Temple is undergoing its most significant renovation since its dedication in 1893. The renovation includes a seismic retrofit of the historic stone structure’s foundations using base isolation. This paper focuses on the temporary underpinning of the 16 to 35 feet thick unreinforced masonry perimeter walls of this massive structure. Conventional needle beam or direct structural underpinning approaches to support the Temple in place during base isolator installation were precluded by its immense weight and extremely thick walls. The design-build team instead developed a unique temporary support of excavation (SOE) program to allow the 19-foot-deep excavations for the new base isolator foundations. The SOE scheme allowed the massive structure to be supported on confined soil “columns” located directly below the masonry wall footings while excavation to construct the new foundations was advanced concurrently along the Temple’s outer perimeter and inside the building. Shoring system stiffness was critical to mitigate settlement risk for this historic building and construction methods were selected to minimize detrimental installation effects. The structural engineer’s permanent design required sequentially jacked steel pipes immediately below the walls, which were filled with post-tensioned reinforced concrete to create transfer beams. After completion of the foundation excavation, two new grade beams separated vertically by base isolators were constructed along both the interior and exterior sides of the perimeter walls. The concrete filled steel pipe transfer beams were structurally connected into the upper grade beams above the isolators. After load transfer is completed, the soil directly below the walls will be excavated to allow free movement of the structure and grade beams above the base isolators in the event of a future earthquake. The historic temple SOE and underpinning system employed multiple construction methods, including micropiles, secant piles, tieback anchors, tensioned tie-rods, temporary attachments to the jacked permanent steel pipes, hand-dug underpinning piers, permeation grouting and steel structural headers supporting interior walls. Design and construction of the historic retrofit SOE system is detailed in this paper.

Authors

Publication Details

Published
2024-10-06
DOI
https://doi.org/10.37308/dfi49.2024310313
Citations
1
Primary Topic
American Constitutional Law and Politics
Type
article
Field-Weighted Citation Impact
2.23
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Underpinning the Salt Lake Temple

Rob Jameson
1 citations
American Constitutional Law and Politics
2.23
article

Underpinning the Salt Lake Temple

Rob Jameson
article en
1 citations

Abstract

The Salt Lake Temple is undergoing its most significant renovation since its dedication in 1893. The renovation includes a seismic retrofit of the historic stone structure’s foundations using base isolation. This paper focuses on the temporary underpinning of the 16 to 35 feet thick unreinforced masonry perimeter walls of this massive structure. Conventional needle beam or direct structural underpinning approaches to support the Temple in place during base isolator installation were precluded by its immense weight and extremely thick walls. The design-build team instead developed a unique temporary support of excavation (SOE) program to allow the 19-foot-deep excavations for the new base isolator foundations. The SOE scheme allowed the massive structure to be supported on confined soil “columns” located directly below the masonry wall footings while excavation to construct the new foundations was advanced concurrently along the Temple’s outer perimeter and inside the building. Shoring system stiffness was critical to mitigate settlement risk for this historic building and construction methods were selected to minimize detrimental installation effects. The structural engineer’s permanent design required sequentially jacked steel pipes immediately below the walls, which were filled with post-tensioned reinforced concrete to create transfer beams. After completion of the foundation excavation, two new grade beams separated vertically by base isolators were constructed along both the interior and exterior sides of the perimeter walls. The concrete filled steel pipe transfer beams were structurally connected into the upper grade beams above the isolators. After load transfer is completed, the soil directly below the walls will be excavated to allow free movement of the structure and grade beams above the base isolators in the event of a future earthquake. The historic temple SOE and underpinning system employed multiple construction methods, including micropiles, secant piles, tieback anchors, tensioned tie-rods, temporary attachments to the jacked permanent steel pipes, hand-dug underpinning piers, permeation grouting and steel structural headers supporting interior walls. Design and construction of the historic retrofit SOE system is detailed in this paper.

Openalex Percentile: Top 8%
American Constitutional Law and Politics
2.23
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.