Analyzing The Impact of Contract Value, Project Duration, and Number of Floors on Human Resource Costs In The Agenci Dejenvolvementu Nacional Office Construction Project In Dili Using Multiple Regression

This study aims to analyze the influence of building construction project financing, which includes contract value, project duration, and number of floors, on human resource costs (Expert Costs, Skilled Labor Costs, and Worker/Mandor Costs) in building construction projects within the Dili City Government Office. The research focuses on 20 building projects in the Dili City Government Office environment. Using project report documents as data, the independent variables in this study are contract value, project duration, and the number of floors, while the dependent variables are the costs associated with experts, skilled labor, and workers/mandors/laden. The study employs multiple linear regression analysis to assess the relationship between these variables. The results show that the contract value has a significant partial effect on human resource costs, including expert costs, skilled labor costs, and worker/mandor costs. This indicates that a higher contract value influences the allocation of human resource costs in building construction projects. In conclusion, the study highlights the importance of managing contract value, project duration, and the number of floors to optimize human resource costs and ensure efficient project completion.

Authors

Institutions

Publication Details

Journal
Asian Journal of Social and Humanities
Published
2025-03-22
DOI
https://doi.org/10.59888/ajosh.v3i6.524
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analyzing The Impact of Contract Value, Project Duration, and Number of Floors on Human Resource Costs In The Agenci Dejenvolvementu Nacional Office Construction Project In Dili Using Multiple Regression

João Antônio Gesser Raimundo, Jaka Purnama, Budi Witjaksana
Asian Journal of Social and Humanities
Construction Project Management and Performance
article

Analyzing The Impact of Contract Value, Project Duration, and Number of Floors on Human Resource Costs In The Agenci Dejenvolvementu Nacional Office Construction Project In Dili Using Multiple Regression

João Antônio Gesser Raimundo, Jaka Purnama, Budi Witjaksana
article en

Abstract

This study aims to analyze the influence of building construction project financing, which includes contract value, project duration, and number of floors, on human resource costs (Expert Costs, Skilled Labor Costs, and Worker/Mandor Costs) in building construction projects within the Dili City Government Office. The research focuses on 20 building projects in the Dili City Government Office environment. Using project report documents as data, the independent variables in this study are contract value, project duration, and the number of floors, while the dependent variables are the costs associated with experts, skilled labor, and workers/mandors/laden. The study employs multiple linear regression analysis to assess the relationship between these variables. The results show that the contract value has a significant partial effect on human resource costs, including expert costs, skilled labor costs, and worker/mandor costs. This indicates that a higher contract value influences the allocation of human resource costs in building construction projects. In conclusion, the study highlights the importance of managing contract value, project duration, and the number of floors to optimize human resource costs and ensure efficient project completion.

Asian Journal of Social and HumanitiesVol. 3(6)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 94%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analyzing The Impact of Contract Value, Project Duration, and Number of Floors on Human Resource Costs In The Agenci Dejenvolvementu Nacional Office Construction Project In Dili Using Multiple Regression — João Antônio Gesser Raimundo, Jaka Purnama, et al. · Asian Journal of Social and Humanities (2025) | TGRS Research Map | TGRS