Project Management Efficiency Strategy for Public Safety Center (PSC) Building in Probolinggo Regency

This research examines the efficiency of managing the construction of the Public Safety Center (PSC) building in Probolinggo Regency. Effective management ensures the project meets its timeline, budget, and quality goals. We used a method called Earned Value Analysis to track progress and identify potential issues early on. Key indicators like the Cost Performance Index (CPI) and Schedule Performance Index (SPI) helped us understand how well the project was performing in terms of cost and schedule. The research revealed challenges such as material delays and labor shortages, which impacted the project's efficiency. By analyzing these issues, we propose solutions to improve project planning and execution, focusing on better resource allocation and scheduling. The findings offer valuable insights for future construction projects, helping to minimize delays and overspending. This research emphasizes the importance of identifying project performance issues promptly to ensure overall success. The recommendations can guide improvements in construction project management, ensuring projects are completed on time, within budget, and to the required quality standards.

Authors

Publication Details

Journal
Journal Of World Science
Published
2025-02-10
DOI
https://doi.org/10.58344/jws.v4i2.1283
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Project Management Efficiency Strategy for Public Safety Center (PSC) Building in Probolinggo Regency

Sajiyo Sajiyo, Andi Patriadi, Lucky Hendra Saputra
1 links
Journal Of World Science
Management and Optimization Techniques
article

Project Management Efficiency Strategy for Public Safety Center (PSC) Building in Probolinggo Regency

Sajiyo Sajiyo, Andi Patriadi, Lucky Hendra Saputra
article en

Abstract

This research examines the efficiency of managing the construction of the Public Safety Center (PSC) building in Probolinggo Regency. Effective management ensures the project meets its timeline, budget, and quality goals. We used a method called Earned Value Analysis to track progress and identify potential issues early on. Key indicators like the Cost Performance Index (CPI) and Schedule Performance Index (SPI) helped us understand how well the project was performing in terms of cost and schedule. The research revealed challenges such as material delays and labor shortages, which impacted the project's efficiency. By analyzing these issues, we propose solutions to improve project planning and execution, focusing on better resource allocation and scheduling. The findings offer valuable insights for future construction projects, helping to minimize delays and overspending. This research emphasizes the importance of identifying project performance issues promptly to ensure overall success. The recommendations can guide improvements in construction project management, ensuring projects are completed on time, within budget, and to the required quality standards.

Journal Of World ScienceVol. 4(2)
Openalex Percentile: Top 93%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Project Management Efficiency Strategy for Public Safety Center (PSC) Building in Probolinggo Regency — Sajiyo Sajiyo, Andi Patriadi, et al. · Journal Of World Science (2025) | TGRS Research Map | TGRS