Analysis of Project Delay Impacts on Time and Cost In Elevator Work For A 10-Story Office Building Construction Project

This study aims to analyze the impact of elevator installation delays on the schedule and budget of a 10-story office building construction project in Gresik. By comparing two scenarios—on-time elevator work versus delayed elevator work—this research uses a comparative analysis approach based on project documentation, interviews with stakeholders, and cost and time data. The findings reveal that delays in elevator work significantly affected the overall project timeline, causing a shift in the schedule and necessitating changes in structural methods, particularly the use of steel instead of concrete for the separator beams. This change expedited construction but increased costs substantially. The study also highlights the cascading effects of these delays, which led to further adjustments in the building's structure and increased labor and material costs. The research emphasizes the importance of early-stage planning, coordination, and the adoption of advanced project management techniques, such as Building Information Modeling (BIM), to minimize risks and ensure timely project completion. In conclusion, the study provides valuable insights into how elevator delays can disrupt construction projects and recommends strategies to mitigate such risks in future developments.

Authors

Institutions

Publication Details

Journal
Devotion Journal of Research and Community Service
Published
2025-03-22
DOI
https://doi.org/10.59188/devotion.v6i3.25437
Primary Topic
Elevator Systems and Control
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Project Delay Impacts on Time and Cost In Elevator Work For A 10-Story Office Building Construction Project

Sajiyo Sajiyo, Turmudi Oktafiansyah, Andi Patriadi
Devotion Journal of Research and Community Service
Elevator Systems and Control
article

Analysis of Project Delay Impacts on Time and Cost In Elevator Work For A 10-Story Office Building Construction Project

Sajiyo Sajiyo, Turmudi Oktafiansyah, Andi Patriadi
article en

Abstract

This study aims to analyze the impact of elevator installation delays on the schedule and budget of a 10-story office building construction project in Gresik. By comparing two scenarios—on-time elevator work versus delayed elevator work—this research uses a comparative analysis approach based on project documentation, interviews with stakeholders, and cost and time data. The findings reveal that delays in elevator work significantly affected the overall project timeline, causing a shift in the schedule and necessitating changes in structural methods, particularly the use of steel instead of concrete for the separator beams. This change expedited construction but increased costs substantially. The study also highlights the cascading effects of these delays, which led to further adjustments in the building's structure and increased labor and material costs. The research emphasizes the importance of early-stage planning, coordination, and the adoption of advanced project management techniques, such as Building Information Modeling (BIM), to minimize risks and ensure timely project completion. In conclusion, the study provides valuable insights into how elevator delays can disrupt construction projects and recommends strategies to mitigate such risks in future developments.

Devotion Journal of Research and Community ServiceVol. 6(3)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 94%
Elevator Systems and Control
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.