Analysis of Mitigation Strategies For Project Delay Factors In The Probolinggo Square Construction

This study aims to analyze the mitigation of factors that cause delays in the Probolinggo City Square construction project, a project that faces challenges in implementation and completion. Delays in construction projects can have various negative impacts, including increased costs, time losses, and reduced quality of project outcomes. Thus, project mitigation becomes the main core in this research. Through this research, it is shown that there are several mitigation measures, such as digitization of administrative processes to speed up approval of materials, improved coordination between parties to reduce conflicts and uncertainties, and more careful planning for additional work and identification of work. In addition, workforce training and the use of more advanced project management technology can improve the efficiency of project implementation. The results of this study are expected to be a reference for parties involved in construction projects, especially in managing the risk of delay. With the implementation of appropriate mitigation measures, construction projects can be more efficient in terms of time, cost, and quality, thus providing maximum benefits for all parties involved.

Authors

Institutions

Publication Details

Journal
Devotion Journal of Research and Community Service
Published
2025-03-22
DOI
https://doi.org/10.59188/devotion.v6i3.25435
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Mitigation Strategies For Project Delay Factors In The Probolinggo Square Construction

Sajiyo Sajiyo, Andi Patriadi, Negarawan Laksana Putra
Devotion Journal of Research and Community Service
BIM and Construction Integration
article

Analysis of Mitigation Strategies For Project Delay Factors In The Probolinggo Square Construction

Sajiyo Sajiyo, Andi Patriadi, Negarawan Laksana Putra
article en

Abstract

This study aims to analyze the mitigation of factors that cause delays in the Probolinggo City Square construction project, a project that faces challenges in implementation and completion. Delays in construction projects can have various negative impacts, including increased costs, time losses, and reduced quality of project outcomes. Thus, project mitigation becomes the main core in this research. Through this research, it is shown that there are several mitigation measures, such as digitization of administrative processes to speed up approval of materials, improved coordination between parties to reduce conflicts and uncertainties, and more careful planning for additional work and identification of work. In addition, workforce training and the use of more advanced project management technology can improve the efficiency of project implementation. The results of this study are expected to be a reference for parties involved in construction projects, especially in managing the risk of delay. With the implementation of appropriate mitigation measures, construction projects can be more efficient in terms of time, cost, and quality, thus providing maximum benefits for all parties involved.

Devotion Journal of Research and Community ServiceVol. 6(3)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 95%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.