Evaluation of Cost and Time Estimates Using The Earned Value Method: A Case Study of The Construction of RU Guest House and Main House

This study evaluates the performance of the RU Guest House and Main House construction project in Bali, focusing on time and cost estimates using the Earned Value Method (EVM). By analyzing the Actual Cost of Work Performed (ACWP), Budgeted Cost of Work Performed (BCWP), and Budgeted Cost of Work Scheduled (BCWS), the study identifies significant delays and cost overruns. The project, initially scheduled for 34 weeks, experienced a 27.99% delay by week 21, with an estimated cost increase of IDR 1,079,046,375. The findings reveal that poor initial planning and logistical constraints, such as narrow access roads for material delivery, contributed to the delays. The study also forecasts an extended completion time of 42 weeks and provides estimates for the total project cost at IDR 13,736,136,610. The results highlight the importance of thorough planning and logistics management to minimize risks. EVM proved to be an effective tool in monitoring and controlling project performance, providing essential insights for improving future project management practices. The study concludes that better planning, logistics, and real-time project performance monitoring are crucial to ensuring project success in both time and budget management.

Authors

Institutions

Publication Details

Journal
Journal Of Social Research
Published
2025-03-22
DOI
https://doi.org/10.55324/josr.v4i4.2488
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Evaluation of Cost and Time Estimates Using The Earned Value Method: A Case Study of The Construction of RU Guest House and Main House

Budi Witjaksana, Hanie Teki Tjendani, Komang Gede Triska Bayu Wedananta
Journal Of Social Research
BIM and Construction Integration
article

Evaluation of Cost and Time Estimates Using The Earned Value Method: A Case Study of The Construction of RU Guest House and Main House

Budi Witjaksana, Hanie Teki Tjendani, Komang Gede Triska Bayu Wedananta
article en

Abstract

This study evaluates the performance of the RU Guest House and Main House construction project in Bali, focusing on time and cost estimates using the Earned Value Method (EVM). By analyzing the Actual Cost of Work Performed (ACWP), Budgeted Cost of Work Performed (BCWP), and Budgeted Cost of Work Scheduled (BCWS), the study identifies significant delays and cost overruns. The project, initially scheduled for 34 weeks, experienced a 27.99% delay by week 21, with an estimated cost increase of IDR 1,079,046,375. The findings reveal that poor initial planning and logistical constraints, such as narrow access roads for material delivery, contributed to the delays. The study also forecasts an extended completion time of 42 weeks and provides estimates for the total project cost at IDR 13,736,136,610. The results highlight the importance of thorough planning and logistics management to minimize risks. EVM proved to be an effective tool in monitoring and controlling project performance, providing essential insights for improving future project management practices. The study concludes that better planning, logistics, and real-time project performance monitoring are crucial to ensuring project success in both time and budget management.

Journal Of Social ResearchVol. 4(4)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 95%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.