Re-design of a railway tunnel intersected by surface rupture of the Erkenek fault segment during the 6 February 2023 Pazarcik (Mw 7.7) Earthquake (Türkiye)

Abstract The T3 Tunnel on the Malatya-Narlı Conventional Railway Route was intersected by the surface rupture during the February 6, 2023 Pazarcık Earthquake (Mw 7.7), and a part of the tunnel was damaged completely. In this study, the investigation results, and re-design of the tunnel, are presented. The T3 Tunnel, which was built in 1933 with interlocking stone masonry lining, was cut by the Erkenek fault, one of the segments of the East Anatolian Fault Zone (EAFZ), and a landslide was triggered around the tunnel portal. Under the influence of these two factors, collapse, and various deformations occurred in the tunnel. To understand the character of the failure, detailed geological, geophysical, and geotechnical studies were carried out in addition to in-situ observations. Subsequently, the tunnel was re-designed and repaired to open the railway to service. For this purpose, a re-design project was developed that included 2-stage engineering solutions including on-tunnel and in-tunnel construction efforts. In the first stage, the portal landslide was rehabilitated using support systems, and in the second stage, tunnel consolidation injection, redesign of the portal structure, and reconstruction of the tunnel support system were carried out. The obtained data and scientific evaluations are presented together with analyses. It is of vital importance that transportation structures continue to function during and after earthquakes. Therefore, the case presented in the study is one of the rare and interesting cases in terms of tunneling literature. The construction efforts in the T3 Tunnel were completed without any problems 6 months after the earthquakes, while more than 30,000 aftershocks continued.

Authors

Institutions

Publication Details

Journal
Bulletin of Engineering Geology and the Environment
Published
2025-03-19
DOI
https://doi.org/10.1007/s10064-025-04217-y
Citations
13
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
12.39

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Re-design of a railway tunnel intersected by surface rupture of the Erkenek fault segment during the 6 February 2023 Pazarcik (Mw 7.7) Earthquake (Türkiye)

Candan Gökçeoğlu, Servet Karahan, Evren Poşluk, F. Burak Büyükdemirci
13 citations
Bulletin of Engineering Geology and the Environment
Geotechnical Engineering and Underground Structures
12.39
article

Re-design of a railway tunnel intersected by surface rupture of the Erkenek fault segment during the 6 February 2023 Pazarcik (Mw 7.7) Earthquake (Türkiye)

Candan Gökçeoğlu, Servet Karahan, Evren Poşluk, F. Burak Büyükdemirci
article en
13 citations

Abstract

Abstract The T3 Tunnel on the Malatya-Narlı Conventional Railway Route was intersected by the surface rupture during the February 6, 2023 Pazarcık Earthquake (Mw 7.7), and a part of the tunnel was damaged completely. In this study, the investigation results, and re-design of the tunnel, are presented. The T3 Tunnel, which was built in 1933 with interlocking stone masonry lining, was cut by the Erkenek fault, one of the segments of the East Anatolian Fault Zone (EAFZ), and a landslide was triggered around the tunnel portal. Under the influence of these two factors, collapse, and various deformations occurred in the tunnel. To understand the character of the failure, detailed geological, geophysical, and geotechnical studies were carried out in addition to in-situ observations. Subsequently, the tunnel was re-designed and repaired to open the railway to service. For this purpose, a re-design project was developed that included 2-stage engineering solutions including on-tunnel and in-tunnel construction efforts. In the first stage, the portal landslide was rehabilitated using support systems, and in the second stage, tunnel consolidation injection, redesign of the portal structure, and reconstruction of the tunnel support system were carried out. The obtained data and scientific evaluations are presented together with analyses. It is of vital importance that transportation structures continue to function during and after earthquakes. Therefore, the case presented in the study is one of the rare and interesting cases in terms of tunneling literature. The construction efforts in the T3 Tunnel were completed without any problems 6 months after the earthquakes, while more than 30,000 aftershocks continued.

Bulletin of Engineering Geology and the EnvironmentVol. 84(4)
Cappadocia University (TR), Turkish Aerospace Industries (Turkey) (TR)
Kapadokya Üniversitesi
Openalex Percentile: Top 1%
Geotechnical Engineering and Underground Structures
12.39
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.