Risk Analysis of The Implementation of Electricity Infrastructure Construction Case Study: Gistet 500 Kv Payton

This research analyzes the construction risks of the 500 kV Paiton High Voltage Substation (GISTET) and develops the most optimal risk treatment based on the risk management standard SNI 8615:2018. The research variables were derived from a literature review, followed by the Delphi Technique questionnaire to identify relevant risks from respondents. Subsequently, a qualitative analysis was conducted using the Consequence/Probability Matrix to identify the dominant risks, followed by a quantitative analysis using the Expected Monetary Value (EMV) calculation. The determination of the most optimal risk treatment for each dominant risk was obtained through Decision Tree Analysis (DTA). The research results identify 38 relevant risks, with 10 classified as dominant, categorized as high, very high, and extreme risks. The three risks with the highest EMV impact values are project execution time not aligning with the project schedule, suboptimal contractor performance, and delays in the arrival and mobilization of materials to be installed. The study's implications underscore the importance of proactive risk management in large-scale construction projects, aiming to minimize potential losses and ensure project success.

Authors

Institutions

Publication Details

Journal
Jurnal Indonesia Sosial Teknologi
Published
2025-03-19
DOI
https://doi.org/10.59141/jist.v6i3.8988
Primary Topic
Risk and Safety Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Analysis of The Implementation of Electricity Infrastructure Construction Case Study: Gistet 500 Kv Payton

Dhimas Widhi Handani, Fahmi Kuncoro
Jurnal Indonesia Sosial Teknologi
Risk and Safety Analysis
article

Risk Analysis of The Implementation of Electricity Infrastructure Construction Case Study: Gistet 500 Kv Payton

Dhimas Widhi Handani, Fahmi Kuncoro
article en

Abstract

This research analyzes the construction risks of the 500 kV Paiton High Voltage Substation (GISTET) and develops the most optimal risk treatment based on the risk management standard SNI 8615:2018. The research variables were derived from a literature review, followed by the Delphi Technique questionnaire to identify relevant risks from respondents. Subsequently, a qualitative analysis was conducted using the Consequence/Probability Matrix to identify the dominant risks, followed by a quantitative analysis using the Expected Monetary Value (EMV) calculation. The determination of the most optimal risk treatment for each dominant risk was obtained through Decision Tree Analysis (DTA). The research results identify 38 relevant risks, with 10 classified as dominant, categorized as high, very high, and extreme risks. The three risks with the highest EMV impact values are project execution time not aligning with the project schedule, suboptimal contractor performance, and delays in the arrival and mobilization of materials to be installed. The study's implications underscore the importance of proactive risk management in large-scale construction projects, aiming to minimize potential losses and ensure project success.

Jurnal Indonesia Sosial TeknologiVol. 6(3)
Sepuluh Nopember Institute of Technology (ID)
Openalex Percentile: Top 94%
Risk and Safety Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.