Time Management Strategies for Construction Work on Site by Contractor during Pandemic

During the Covid-19 pandemic, the Malaysian government implemented a Movement Control Order (MCO), mandating that all enterprises function remotely. However, the construction industry requires hands-on and on-site work, particularly for contractors. On May 4, 2020, the Ministry of International Trade and Industry (MITI) permitted several industries, including the construction sector, to resume work by following Standard Operating Procedures (SOPs) based on MITI and Construction Industry Development Board (CIDB) guidance to ensure projects were safe to recommence. The implementation of SOPs at construction sites has added increased pressure, particularly on contractors, concerning managing work progress, such as time management, where productivity is restrained. This study aims to develop comprehensive strategies for contractors in terms of time management to ensure on-site construction work delivery within the specific time stated in the contract. Its objective is to ascertain the procedures employed by contractors managing construction work time on-site during the Covid-19 pandemic in Malaysia, identify the challenges faced, and develop comprehensive strategies for contractors' time management for construction work at the construction site during the Covid-19 pandemic in Malaysia. The study was conducted via literature review and questionnaire surveys. The research findings provide knowledge to the construction industry, particularly contractors, about time management for site work and provide available strategies to overcome challenges faced during construction work during the Covid-19 pandemic. Keywords: Construction work, COVID-19 Pandemic, On-site, Strategies, Time management.

Authors

Institutions

Publication Details

Journal
Global Conference on Business and Social Sciences Proceeding
Published
2024-09-09
DOI
https://doi.org/10.35609/gcbssproceeding.2024.1(63)
Primary Topic
Urban Transport Systems Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Time Management Strategies for Construction Work on Site by Contractor during Pandemic

Puteri Nur Farah Naadia Mohd Fauzi, Muhammad Nazirul Pasaruddin
Global Conference on Business and Social Sciences Proceeding
Urban Transport Systems Analysis
article

Time Management Strategies for Construction Work on Site by Contractor during Pandemic

Puteri Nur Farah Naadia Mohd Fauzi, Muhammad Nazirul Pasaruddin
article en

Abstract

During the Covid-19 pandemic, the Malaysian government implemented a Movement Control Order (MCO), mandating that all enterprises function remotely. However, the construction industry requires hands-on and on-site work, particularly for contractors. On May 4, 2020, the Ministry of International Trade and Industry (MITI) permitted several industries, including the construction sector, to resume work by following Standard Operating Procedures (SOPs) based on MITI and Construction Industry Development Board (CIDB) guidance to ensure projects were safe to recommence. The implementation of SOPs at construction sites has added increased pressure, particularly on contractors, concerning managing work progress, such as time management, where productivity is restrained. This study aims to develop comprehensive strategies for contractors in terms of time management to ensure on-site construction work delivery within the specific time stated in the contract. Its objective is to ascertain the procedures employed by contractors managing construction work time on-site during the Covid-19 pandemic in Malaysia, identify the challenges faced, and develop comprehensive strategies for contractors' time management for construction work at the construction site during the Covid-19 pandemic in Malaysia. The study was conducted via literature review and questionnaire surveys. The research findings provide knowledge to the construction industry, particularly contractors, about time management for site work and provide available strategies to overcome challenges faced during construction work during the Covid-19 pandemic. Keywords: Construction work, COVID-19 Pandemic, On-site, Strategies, Time management.

Global Conference on Business and Social Sciences ProceedingVol. 16(1)
Northumbria University (GB), Jabatan Perkhidmatan Awam Malaysia (MY)
Openalex Percentile: Top 69%
Urban Transport Systems Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Time Management Strategies for Construction Work on Site by Contractor during Pandemic — Puteri Nur Farah Naadia Mohd Fauzi, Muhammad Nazirul Pasaruddin · Global Conference on Business and Social Sciences Proceeding (2024) | TGRS Research Map | TGRS