Experience System to Solve Problems in Emergency Reconstruction Projects

Introduction: This study aims to create an expert system questionnaire and assess the potential impact of delays and project cost changes after disasters. These are important considerations for achieving sustainable development goals and restoring normalcy to communities affected by natural disasters like earthquakes, floods, and fires, environmental crises such as the Covid-19 pandemic, or man-made disasters like wars. Objectives: The study focuses on construction projects in Iraq after the 2003 war. This hypothesis of this paper came to suggest that utilizing an experience-based system, such as a knowledge-sharing or decision-support system, will help address the challenges faced during the rebuilding process after a disaster, and these challenges extend to include time constraints and limited resources, besides the necessity of faster decision making. There might be no effectiveness in traditional construction projects as in an emergency reconstruction projects scenario; therefore, innovative methodology such as experience system could be crucial. Methods: The expert system questionnaire was developed based on input from Iraqi experts and consultants in the construction industry. It includes 80 potential causes of delay, categorized into major and secondary factors. This methodology is being applied for the first time in project management in Iraq. Results: The results revealed that the main contributors to project delays are contractors, owners, external factors, consulting teams, and systems and instructions, with contribution ratios of 30, 20, 15, 10, and 7.5, respectively. The analysis also showed that secondary factors have a higher linear correlation value than primary factors. Conclusions: The study found that contractors and external factors, such as those seen in the Covid-19 pandemic, have the most significant impact on project delays, while other factors play a lesser role in project implementation delays.

Authors

Publication Details

Journal
Journal of Information Systems Engineering & Management
Published
2025-03-11
DOI
https://doi.org/10.52783/jisem.v10i18s.2892
Citations
1
Primary Topic
Knowledge Management and Technology
Type
article
Field-Weighted Citation Impact
2.11
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Experience System to Solve Problems in Emergency Reconstruction Projects

Rasha Waheeb
1 citations
Journal of Information Systems Engineering & Management
Knowledge Management and Technology
2.11
article

Experience System to Solve Problems in Emergency Reconstruction Projects

Rasha Waheeb
article en
1 citations

Abstract

Introduction: This study aims to create an expert system questionnaire and assess the potential impact of delays and project cost changes after disasters. These are important considerations for achieving sustainable development goals and restoring normalcy to communities affected by natural disasters like earthquakes, floods, and fires, environmental crises such as the Covid-19 pandemic, or man-made disasters like wars. Objectives: The study focuses on construction projects in Iraq after the 2003 war. This hypothesis of this paper came to suggest that utilizing an experience-based system, such as a knowledge-sharing or decision-support system, will help address the challenges faced during the rebuilding process after a disaster, and these challenges extend to include time constraints and limited resources, besides the necessity of faster decision making. There might be no effectiveness in traditional construction projects as in an emergency reconstruction projects scenario; therefore, innovative methodology such as experience system could be crucial. Methods: The expert system questionnaire was developed based on input from Iraqi experts and consultants in the construction industry. It includes 80 potential causes of delay, categorized into major and secondary factors. This methodology is being applied for the first time in project management in Iraq. Results: The results revealed that the main contributors to project delays are contractors, owners, external factors, consulting teams, and systems and instructions, with contribution ratios of 30, 20, 15, 10, and 7.5, respectively. The analysis also showed that secondary factors have a higher linear correlation value than primary factors. Conclusions: The study found that contractors and external factors, such as those seen in the Covid-19 pandemic, have the most significant impact on project delays, while other factors play a lesser role in project implementation delays.

Journal of Information Systems Engineering & ManagementVol. 10(18s)
Openalex Percentile: Top 15%
Knowledge Management and Technology
2.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Experience System to Solve Problems in Emergency Reconstruction Projects — Rasha Waheeb · Journal of Information Systems Engineering & Management (2025) | TGRS Research Map | TGRS